Underground Mining - Sinking and Commissioning of the Eastern Twin Shaft System at Buffelsfontein Gold Mining Co, Ltd

- Organization:
- The American Institute of Mining, Metallurgical, and Petroleum Engineers
- Pages:
- 16
- File Size:
- 1086 KB
- Publication Date:
- Jan 1, 1964
Abstract
The Buffelsfontein Gold Mining Company is situated in the Klerksdorp district of the Province of the Transvaal in the Republic of South Africa, approximately 100 miles west of Johannesburg. Gold production commenced in January 1957 and Uranium treatment of residue slimes as a by-product started in July 1957. The mining property is 5435 mining claims in extent, the equivalent of 7988 acres or 12.5 sq miles. The mine was initially exploited by the Pioneer Twin Shaft System, consisting of a 26-ft diam down-cast shaft and a 22 ft-diam up-cast shaft, sunk in the north-west area of the mine to cater for the hoisting and ventilation requirements for a milling rate of 150,000 tons per month. To exploit the Eastern zone of the property and assist in increasing production to 200,000 tons milled per month, it was decided to sink a further Twin Shaft System consisting of a 28-ft diam downcast shaft and a ventilation up-cast shaft -22-ft in diam, both monolithic concrete lined — 200 ft apart and 5300 ft deep. This paper deals with the sinking and commissioning of these Eastern Twin Shafts. This was achieved by one sinking crew within a period of 20 months. A) PLANNING 1) Siting: The Eastern Shaft System was sited in the north-east area of the property, 12,000 ft east on strike from the Pioneer System. (Fig. 1). Initially the system was sunk to the 5300 ft elevation to conform with the original Pioneer Shaft System. On completion a sub-vertical main shaft will be sunk to the 8000 ft elevation in the immediate vicinity, and subsequently the surface ventilation shaft will be deepened to this elevation by raising from level to level and sliping to full size. The exact positions of the shafts were chosen after: a) underground development had located certain known water bearing zones, and b) geophysical and topographical surveys had been carried out. The shafts passed through the following geological succession: Surface to 4430 ft - Dolomites of the Transvaal System 4430 to 4470 ft - Quartzites and conglomerates of the Black Reef Series of the Transvaal System. 4470 to 4470 ft - Diabasic Lava of the Venters-dorp System (Ventersdorp Contact Reef at base). 4470 to 5250 ft - Quartzites of the Elsburg Series of the Upper Witwaters-rand System. The shafts were sited to ensure that the least possible water would be encountered during sinking, and this contributed to the rapid rate of sinking. 2) Duties: a) The 22-ft diam ventilation shaft was designed to up-cast 1,400,000 cfm of air (0.060 density) against a resistance of 22 in. water gauge. b) The main shaft was designed to handle 160,000 tons hoisted per month as well as the men, material and down-cast ventilation to serve this tonnage. The 284 diam main shaft is equipped with streamlined buntons spaced at 15 ft centers set in pockets which were left during sinking. There are six compartments, four of which are sewed by two dual purpose hoists, hoisting either, twedeck man cages or 13-ton bottom discharge skips. The other two compartments are served by a single purpose winder hoisting double deck cages accommodating 60 men per deck. (Fig. 2). 3) Timing: Permanent equipment was ordered well in advance to insure continuity in the operation. Development underground reached the shaft positions before the start of sinking operations. From this development, boreholes were drilled into shaft positions to drain off water in the vicinity of the shafts. To ensure complete co-ordination of effort, all relevant data, as well as the allocation of responsibility, were made known to all persons and departments concerned. 4) Models: The extensive use of scale models during the preliminary planning stages proved most useful in deciding on design such as buntons, bunton pockets and guide cleats, and complex layouts concerning loading, spillage and pumping arrangements. (Fig. 3). These models also proved invaluable in determining the walling routine. Normal working conditions could
Citation
APA:
(1964) Underground Mining - Sinking and Commissioning of the Eastern Twin Shaft System at Buffelsfontein Gold Mining Co, LtdMLA: Underground Mining - Sinking and Commissioning of the Eastern Twin Shaft System at Buffelsfontein Gold Mining Co, Ltd. The American Institute of Mining, Metallurgical, and Petroleum Engineers, 1964.