Trolley assist aids haulage at Iscor’s Sishen iron mine in South Africa

- Organization:
- Society for Mining, Metallurgy & Exploration
- Pages:
- 3
- File Size:
- 392 KB
- Publication Date:
- Jan 4, 1986
Abstract
Introduction The South African Iron and Steel Co. Ltd., in Sishen, operates a large iron ore mine in the Cape Province of the Republic of South Africa. The mine is about 600 km (370 miles) west of Johannesburg. Its annual capacity is 100 Mt (110 million st) of ore and waste. Present production is 60 Mt/a (66 million stpy). The mine operates continuously six days a week. Primary equipment includes 55 154 t (170 st) Wabco and Unit Rig trucks and 14 P&H shovels. During 1979, a feasibility study into the application of a trolley assist system was launched. This was due to the escalation in diesel fuel costs and the appeal by the South African government to reduce the use of fossil fuels. Tests and economic evaluations proved the system technically feasible. The estimated discounted cash flow return exceeded 50%. Diesel fuel consumption would be reduced by 120 ML (31.7 million gal) in the next 10 years. The construction of 7.7 km (4.8 miles) of line and the conversion of 66 154 t (170 st) trucks were completed in March 1982. System description The conventional 154 t (170 st) diesel electric rear-dump haul-truck is equipped with two direct current wheelmotors in the rear axle. They drive the rear wheels through planetary gearboxes. A 1.2-MV (1600-hp) diesel engine and an alternator is used to power the wheelmotors. The trolley assist system consists of an overhead power line, a current collector mounted on the truck, and add-on control equipment where external electric power is routed by way of the current collector to the motorized wheels. The diesel engine is used to propel the truck on level sections. On inclines, the wheel-motors of the truck are coupled by way of a current collector to the externally generated electrical power supply for propulsion. The diesel engine, having lower output than the wheelmotors, limits the truck performance. Previously, maximum output was required from an engine on inclines. By supplying the wheelmotors from a virtually unlimited outside electric energy source, the truck performance is enhanced to the extent that speed is increased by 46% and fuel consumption reduced by 75%. System design The unique operational requirements of this mine rendered the already proven trolley pole system useless. Minimum loss in truck mobility and flexibility was required. Overhead lines and substations were required to be relatively light and portable. This enables fast repositioning of a line with no loss in material. These unique specifications set the base for the design of the Sishen system. Steel I-beams, 203 x 203 mm x 52 kg/m (8 x 8 in. x 35 lb per ft) with lengths varying from 8.3 to 11.3 m (27 to 37 ft), mounted on base plates about 4 x 2.6 m (13 x 8.6 ft) were used as masts. The masts were erected at about 50 m (165 ft) and the base plates covered with about 12 t (13 st) of iron ore to keep them absolutely stable. Results from the pilot installations indicated that using single cantilever cross arms for insulator and overhead conductor suspension was not practical. The tension in the overhead varied too much with temperature changes, causing too much sag in the lines. There had to be a positive and negative conductor. It was decided to suspend each polarity on an independent cantilever and keep the conductors under constant tension by weights acting through a two-to-one pulley tensioning arrangement. For each overhead conductor, a standard 160-mm (6.5-sq in.) grooved copper railway conductor was used. To obtain the necessary current carrying capacity, two of these conductors are used in parallel per pole. Insulators are rated at 4 kV and are of the composite type. An 11-kV three-phase line, supported by the pantograph line masts on the opposite side of the dc line, feeds the rectifier stations. The rectifier stations consist of an 11-kV to 860-V, three-phase 1.46 MVA transformer and a three-phase diode bridge rectifier. The output voltage is 1200 V do earthed through a current limiting resistance network so that the line po-
Citation
APA:
(1986) Trolley assist aids haulage at Iscor’s Sishen iron mine in South AfricaMLA: Trolley assist aids haulage at Iscor’s Sishen iron mine in South Africa. Society for Mining, Metallurgy & Exploration, 1986.