Progress on this project will be verbally reported and a description given of the main features. A detailed feasibility study was completed in December 1986, and the Joint Venture has issued an Environmental Impact Statement. This was open for public comment until 16 February. Issues presently being considered include economic justification traffic, air quality, noise, marine fauna and flora, visual impact, heritage and construction impact. Detail design and construction is likely to commence in mid 1987, following determination of the above matters.