The Chemwes uranium plant was designed and constructed within fifteen months; commissioning started during. June 1979, and the plant was producing at design capacity four months later. This account highlights the procedures and methods adopted to bring the plant Into production. The description of the various phases includes some details of the early evaluation, and the feasibility and optimization studies; of the financing, project management, design, construction, and commissioning of the plant; and of the training of personnel. Some of the mistakes made and the factors that contributed to the success are also listed.
Citation
APA:
(1981) The evaluation, design and construction of the uranium plant for Chemwes LimitedMLA: The evaluation, design and construction of the uranium plant for Chemwes Limited. The Southern African Institute of Mining and Metallurgy, 1981.