Soil Mixing for the LPV-111 Levee Improvements, New Orleans: A Case History

- Organization:
- Deep Foundations Institute
- Pages:
- 10
- File Size:
- 1775 KB
- Publication Date:
- Jan 1, 2015
Abstract
"The US Army Corps of Engineers selected the Deep Mixing Method (DMM) for the required stabilization at the LPV 111 Project (New Orleans, USA). DMM was used for ground improvement/foundation strengthening and consequently to stabilize and support the burden of the new levee. Two different technologies were used: Trevi Turbo Mix (TTM) and Contrivance Innovation Cement Mixing Columns (CI-CMC). LPV 111 is the largest soil mixing project to date in the USA with its more than 18,000 elements installed to a depth of up to 67 feet for a total of 1.7 million cubic yards of treated soil. The preparation and execution of the project presented many challenges from various points of view. The little time available to complete the job led to the simultaneous utilization of eight deep mixing rigs and batch plants which worked 24 hours per day, 5.5 days per week on a stretch of land approximately 5.3 miles long. Given the imposing geographical extent of the project, a four phase laboratory programme and five field validation test programmes, conducted in as many different areas of the project, were completed to design and optimize the grout mixes and the installation parameters. The massive quality control/quality assurance testing programme produced over 500 drilled core holes and over 5,000 tested specimens in order to determine unconfined compressive strength (UCS) and uniformity of the DMM elements. This paper has the purposes of describing the tremendous challenges encountered and providing valuableinformation that may be useful for other future projects, including details not previously published.INTRODUCTIONReach LPV-111 is part of the Lake Pontchartrain and Vicinity Hurricane Protection System designed to protect the city of New Orleans and the surrounding areas from the surge that would accompany a 100 year hurricane event. LPV-111 measures approximately 8.5 km (5.3 miles) long, of which 7.2 (4.5 miles) extend along the north bank of the Gulf Intracoastal Waterway (GIWW) and the remaining 1.3 (0.8 miles) run north and terminates at the CSX Railroad Gate. The Bayou Sauvage National Wildlife Refuge borders the levee on both sides (Fig. 1)."
Citation
APA:
(2015) Soil Mixing for the LPV-111 Levee Improvements, New Orleans: A Case HistoryMLA: Soil Mixing for the LPV-111 Levee Improvements, New Orleans: A Case History. Deep Foundations Institute, 2015.