Shoring of Long Beach Main Pump Station Utilizing Ground Improvement Methods, Long Beach, CA

- Organization:
- Deep Foundations Institute
- Pages:
- 11
- File Size:
- 1708 KB
- Publication Date:
- Jan 1, 2017
Abstract
"Condon-Johnson & Associates, Inc. (CJA) with the assistance of design consultant, Brierley Associates, designed and installed a water tight shoring system utilizing several ground improvement techniques jointly. Prior to the installation of the shoring system, a test program consisting of the installation and testing of 7 jet grout columns; 1 soil mix panel; 7 soil anchors and 3 tie downs was performed to verify design assumptions. State-of-the-art quality control measures were employed throughout the project.The shoring system consisted of:•,Deep Soil Mixing (DSM) wall utilizing triple axis tooling to install overlapping columns along the perimeter of the proposed excavation to a treatment depth of 54 feet.•,Installation of steel piles in DSM to provide rigidity to the wall.•,Installation of a jet grout bottom seal, installed from surface to a depth of 58 feet below existing grade.•,Installation of 153 soil anchors, 1-1/4” diameter and 47’-6” length, to tie the jet grout bottom seal to the native soil below to resist hydrostatic uplift, installed from existing grade to a depth of 91 feet.•,Installation of walers and pipe struts for internal bracing•,Installation and stressing of 117 tie downs, 1” diameter and 16 ft length, to tie the pump station mat slab to the jet grout bottom seal, installed from inside the excavated pit.Subsurface conditions at the site consist of uncontrolled fill materials to a depth of 20 feet comprised of sandy silt and clayey sand. The native soils underlying the fill generally consist of soft and compressible lean clay and silt with varying amounts of sands to a depth ranging from approximately 44 to 54 feet below ground surface, which in turn are underlain by dense to very dense silty sand. The groundwater elevation at the site is approximately 8 feet below ground surface.This paper covers the design aspects, construction, and quality control measures undertaken by the geotechnical contractor, with supporting figures.INTRODUCTIONThe owner, County Sanitation District No. 2 of Los Angeles County, designed upgrades to their existing Long Beach Main Pumping Plant Facility. The upgrades consist of a new pump station that includes a reinforced concrete below-grade wet well and dry well, a two-story operations building, two 78-inch diameter pipe inlets, two 42-inch diameter discharge pipelines connecting the existing manifold, two pipe junction structures, two insert-type junction structures, and electrical transformers. This paper focuses on the excavation shoring for the new pump station. The original shoring design concept for the pump station excavation illustrated on the contract plans consisted of pressed in sheet piles, a jet grouted bottom seal with soil anchors, 2 levels of internal bracing, and tie-down anchors to resist hydraulic uplift forces on the buried pump station."
Citation
APA:
(2017) Shoring of Long Beach Main Pump Station Utilizing Ground Improvement Methods, Long Beach, CAMLA: Shoring of Long Beach Main Pump Station Utilizing Ground Improvement Methods, Long Beach, CA. Deep Foundations Institute, 2017.