Shaft Sinking Today - A Boring Business Tomorrow

The American Institute of Mining, Metallurgical, and Petroleum Engineers
Maurice Grieves
Organization:
The American Institute of Mining, Metallurgical, and Petroleum Engineers
Pages:
6
File Size:
856 KB
Publication Date:
Jan 1, 1982

Abstract

The great majority of shafts constructed today are still excavated by drilling and blasting, a method which changed very little in over 100 years until the introduction of the mechanical lashing unit and cactus grab by the South Africans, which enabled muck to be removed as fast as massive hoisting systems could handle it and resulted in very rapid rates of sinking. Record breaking month's performances were achieved at -Hartebeestfontein No. 4 shaft, October 1960-337.1 m; Western Reefs No. 4 shaft, October 1961-340.7 m; and Buffelsfontein eastern twin shaft, March 1962-381.2m. The method was very labor-intensive, requiring a crew of over 60 workers at the shaft bottom during the drill cycle. Safety precautions were strict, but in the drive to achieve rapid advance, cases of personal injury were still somewhat high because of the large number of people engaged in this potentially hostile environment. The South African method, as it came to be referred to throughout the rest of the world, was adopted in the United Kingdom in the late 1950s in a modified form with greatly reduced manpower and nonsimultaneous sinking and lining, which was insisted on by the British Mines Inspectorate. In that instance, it was successfully used to sink the 7.3-m-diam concrete-lined shafts at Kellingley to 770 m depth, with rates of advance of over 90 m/month achieved, a British record at that time. During the sinking of the 1.15-km-deep twin shafts at Boulby potash mine in the UK in 1970, the method was again used, but for the first time ever in Britain exemptions from the mining code permitted the use of crash beams, crash doors, jack catches, and semi-simultaneous sinking and lining techniques. New British shaft sinking records of over 120 m/month were achieved in both shafts. Similar equipment and techniques were used in the early 1970s to sink several deep shafts in Canada, notably Creighton #7 and the Con zinc mine at Yellowknife in the NW Territories. Today, this equipment is standard for deep shafts in the US and the rest of the world. However, with the tremendous escalation in mining labor costs, the impact of health and safety legislation, and environmental regulations, coupled with a very real shortage of miners willing to work in this exposed situation it was apparent that an alternative to the labor-intensive conventional method of shaft construction had to be found. Recognizing the trend is inevitable, one or two major German shaft sinking contracting firms began to take a fresh look at full face boring techniques applied to tunnels and raise bored shafts. The results were most encouraging. Tunnel drivage techniques using moles had developed considerably from Colonel Beaumont's original channel tunnel machine circa 1880 to the superbly engineered Priestley machine selected to cut the British side in 1975 and the double shielded Robbins Grandori borer on the French side of the English Channel. Full face tunnel machines were being successfully used to drive uphill in inclined shafts in Austria and Switzerland. At Mapprag in Switzerland, the Demag mole drove the first (intentional) vertical transition and curve, and then went on to successfully complete the 730-m-long penstock shaft at an inclination of 35°. In Austria, the Wirth mole drove the Kaprun Glacier ski-lift railcar tunnel at record breaking rates of 457 m/MONTH (best 30 m/d) through green schist at an inclination of 29° for a distance of 3.35 km while the Hydro tunnel at Sarrelli in Switzerland was being driven by the Robbin's mole at an inclination of 35°. Simultaneously, extremely promising results were obtained using large assemblies of cutter discs on raise borer heads, such as the 4.87-m-diam X 460-m-deep shaft raised by Teton for Jim Walter Resources Inc. Bearing in mind that most mine shafts in the future (unless in exceptionally competent rock) will require some form of lining, and the trend will be toward deeper shafts as the more easily accessible mineral deposits become exhausted, it was seen that normal raise boring had definite limitations in vertical accuracy, in the limitation imposed by the drill string on the available torque that could be applied to the cutter head, and in the risk of collapse of the unsupported shaft rock wall in friable or jointed and fissured ground, since it is not possible to apply any form of temporary support until the permanent lining is being installed. A further problem was the economics of installing a subsequent lining, necessitating setting up a headgear and hoisting arrangement approaching in size that required for conventional drill and blast sinking and lining. Because of the economics, German contractors opted for a phased transition from drill and blast to the full face, rodless, out of the solid shaft mole, by starting off with a down-the-hole shaft boring machine -without a drillstring-but using a pilot hole to get rid of the muck.
Citation

APA: Maurice Grieves  (1982)  Shaft Sinking Today - A Boring Business Tomorrow

MLA: Maurice Grieves Shaft Sinking Today - A Boring Business Tomorrow. The American Institute of Mining, Metallurgical, and Petroleum Engineers, 1982.

Export
Purchase this Article for $25.00

Create a Guest account to purchase this file
- or -
Log in to your existing Guest account