Salt Lake City Paper - Flotation and the Park-Utah Mine

- Organization:
- The American Institute of Mining, Metallurgical, and Petroleum Engineers
- Pages:
- 3
- File Size:
- 119 KB
- Publication Date:
- Jan 1, 1928
Abstract
UP to June, 1923, the Park-Utah mine had shipped about 94,000 tons of a direet-smelting ore of a gross value of $4,200,000, or about $45. a ton. These values were in gold and silver only, although the ore carried small amounts of lead, copper and zinc. Freight, treatment and deductions had averaged $15.40 a ton. At the expiration of the Pittman Silver Act there was in sight about 30,000 tons of a similar ore with a gross value of about $15 a ton in gold and silver, and a large body of partly developed lead-zinc ore of a gross value of about $20 a ton, 40 per cent. of which was represented by the lead-zinc content and the balance by the silver and gold. Mine costs had been high during the life of the Pittman Act, but as a large part of the profits had gone into equipment of the mine and the orebodies were large and had good walls, we knew that mine costs could be greatly reduced. We were therefore faced by the necessity of getting lower freight and smelter rates or of concentrating the ore. We did obtain better freight rates on lower grade ore, and a favorable smelting rate on the small tonnage of siliccous silver-gold ore, but this smelter rate could not be applied to the lead-zinc ore with any profit to ourselves. The Judge mill of the Park City Mining & Smelting Co., with which we were affiliated, was running to capacity; if we built our own mill it ineant a 5-mile freight haul to a satisfactory millsite and a year's delay. Fortunately, the International Sillelting Co. had just inherited a mill at Tooele which, with some changes, was about double the catpscity required for its own ores. Flotation tests were run on Park-Utah ore and a contract entered into with a low base treatment charge per ton, the tariff being largely fixed by the metallurgical deductions. This contract has been admirably calculated so that the miner can follow a lean orenbody to its limit. Such a procedure has no doubt made it difficult for the smelting company at times, but it has resulted in finding ore extensions that otherwise might have been missed, so In the long run it has profited too. A flat rate per ton would have been like mining up to the claim endlines in a great many of the stopes. In order to offer such a contract it can be inferred that the smelting company must have been able to make high reeoveries and high-grade products on a very lean ore.
Citation
APA:
(1928) Salt Lake City Paper - Flotation and the Park-Utah MineMLA: Salt Lake City Paper - Flotation and the Park-Utah Mine. The American Institute of Mining, Metallurgical, and Petroleum Engineers, 1928.