Rehabilitation, Recommissioning and Upgrading of the Leinster Nickel Concentrator
 
    
    - Organization:
- The Australasian Institute of Mining and Metallurgy
- Pages:
- 10
- File Size:
- 541 KB
- Publication Date:
- Jan 1, 1991
Abstract
In January 1989, Western Mining Corporation (WMC) acquired the  Perseverance and Rocky's Reward orebodies and associated infrastructure  from the Agnew Mining Company (AMC). AMC had closed the  operation in August 1986 and it had been on care and maintenance since  that time. To return the operation to full production as quickly as possible  it was planned to mine the Rocky's Reward orebody by opencut mining  and treat this ore whilst the underground Perseverance workings were  rehabilitated. Removal of overburden from Rocky's Reward thus  commenced immediately with a target of April 1989 for delivery of the  first ore to the concentrator. Extensive rehabilitation and upgrading of the concentrator commenced in  late January, and continued in stages for an 18 month period. The first  stage consisted of overhauling all existing equipment and completing a  crusher upgrade commenced by AMC prior to the mine closure. During  this period, it was necessary to recruit a workforce and re-establish all the  required support structure. In late April the plant commenced  commissioning trials on mullock. The first ore was crushed on the 11th  May 1989 and concentrate produced the following day. From May 1989 to June 1990 the plant was producing nickel concentrate  whilst further upgrading continued. During this period, the flotation  capacity was tripled by installation of a bank of eight Wemco 144L  flotation cells in rougher-scavenger duties and two 12 metre by 2 metre  diameter columns in cleaning duties. The existing vacuum drum filters  were replaced by two Larox PF32 pressure filters, eliminating the need  for solar drying and allowing the flash drier to be fed direct from the  filters. These, along with a major borefield expansion and further work to  the crusher increased the nominal plant capacity from 600,000 to  1,000,000 t/yr. The plant achieved the 1,000,000 t/yr rate in April 1990.
Citation
APA: (1991) Rehabilitation, Recommissioning and Upgrading of the Leinster Nickel Concentrator
MLA: Rehabilitation, Recommissioning and Upgrading of the Leinster Nickel Concentrator. The Australasian Institute of Mining and Metallurgy, 1991.
