Redefining Settlement Control Industry Standards with Modern Mechanized EPB Tunnelling - Eglinton Crosstown LRT Tunnel Case Study

- Organization:
- Society for Mining, Metallurgy & Exploration
- Pages:
- 10
- File Size:
- 760 KB
- Publication Date:
- Jan 1, 2016
Abstract
"The Eglinton Crosstown Light Rail (LRT) Project is part of an $8.4 billion investment to expand transit in the Toronto, Canada area and is the largest transit project initiated in Province’s history. Settlement control and impact to over 1400 adjacent structures due to tunnelling was identified early as a critical project risk. The ground conditions along the 10km tunnel alignment consist of water bearing soft ground deposits (clays, sands, silts) which required careful analysis and control during design and construction. This paper will describe the process used to analyze settlements along the numerous of adjacent structures and evaluate achieved settlement results to those used during design. The paper will demonstrate that with the appropriate design specifications, selection of modernized EPB machines, and contractor performance, settlement can be maintained well below typical industry (volume loss) standards, expanding the application and suitability of soft ground tunnelling in sensitive settlement areas. INTRODUCTION The Eglinton Crosstown Light Rail Transit (LRT) Project is part of an $8.4 billion (2010$ CND) investment from the Ontario provincial government to expand transit in the Toronto, Canada area. The project is being developed by Metrolinx, an agency of the Government of Ontario to provide 19 kilometers of dedicated LRT service connecting the City of Toronto from the west to east along Eglinton Avenue. Upon completion in the year 2020, the Crosstown will be the first LRT constructed in Toronto. It will link regional and local transit, cut travel time along the route by half and provide over a thousand jobs during construction."
Citation
APA:
(2016) Redefining Settlement Control Industry Standards with Modern Mechanized EPB Tunnelling - Eglinton Crosstown LRT Tunnel Case StudyMLA: Redefining Settlement Control Industry Standards with Modern Mechanized EPB Tunnelling - Eglinton Crosstown LRT Tunnel Case Study. Society for Mining, Metallurgy & Exploration, 2016.