Recent Experiences of Continuous Casting at Highveld Steel and Vanadium Corporation Limited

- Organization:
- The Southern African Institute of Mining and Metallurgy
- Pages:
- 9
- File Size:
- 749 KB
- Publication Date:
Abstract
Vanadium slag production in the shaking ladles started in April 1968, steelmaking was begun in July 1968 and the first continuously cast blocks were produced soon after on the 29th July, 1968. Nominal monthly production of over 20 000 tons was reached in seven months and by December 1970 about 12 000 heats were cast and a monthly production of 35000 tons has been achieved.
Citation
APA:
Recent Experiences of Continuous Casting at Highveld Steel and Vanadium Corporation LimitedMLA: Recent Experiences of Continuous Casting at Highveld Steel and Vanadium Corporation Limited. The Southern African Institute of Mining and Metallurgy,