Rabbit Lake project - milling and metallurgy

- Organization:
- Canadian Institute of Mining, Metallurgy and Petroleum
- Pages:
- 7
- File Size:
- 4677 KB
- Publication Date:
- Jan 1, 1989
Abstract
"Since its startup in 1975, the Rabbit Lake mill has been modified (0 process both increased tonnage and higher grade ore. Ore initially came from the Rabbit Lake pit . In 1985, a major mill expansion was commissioned to allow treatment of B-zone pit ore, which is mineralogically and metallurgically different fromRabbit Lake pit ore.Mill modifications, and the changing ore characteristics and processing targets which made them necessary, are described. Mill LocationThe mill complex, shown in Figure I, comprised of milling facilities, acid plant, power generation , warehouse and administration offices, is located approximately 1.5 Ian south of the Rabbit Lake pit, and about 8 Ian southwest of the B-zone open pit mine.Original Milling CircuitOre feed to the mill commenced June 10, 1975. The mill was designed to process 1500 tonnes per day , 483 000 tonnes per year with an average grade of O.44OJo Ups and an annual production of 2000 tonnes UPs' Run-of-mine ore was dumped directly onto a 60 em square opening grizzly. Oversize was broken with an Ingersoll-Rand hydrauli c rock breaker. Minus 60 cm ore was fed to a 6 m diameter by 1.8 m long Hardinge semi-autogenous (SAG) grate discharge mill. Mill discharge was screened over a Tyler double-deck vibrating screen, with screen oversize returned to the SAG mill feed chute via conveyor belt. Screen undersize (minus 2.4 mm) was pumped to 51 cm diameter Krebs cyclones in closed circuit with the SAG mill. Cyclone overflow (about 50% minus 74 micron) was thickened to 55% solids in a 30 m diameter neutral thickener .Thickened pulp was stored in two mechanically-agitated wood stave tanks (5.5 m diameter by 6 m high), to which sulphuric acid was added to obtain a pH range of 1.5 to 2.0. The fmalleaching was carried out in five more identical tanks. Sulphuric acid and sodium chlorate were used to maintain a pH of 1.5 and a terminal emf of -450 to -500 mV. Steam sparge was utilized to obtain a temperature of 45°C."
Citation
APA:
(1989) Rabbit Lake project - milling and metallurgyMLA: Rabbit Lake project - milling and metallurgy. Canadian Institute of Mining, Metallurgy and Petroleum, 1989.