Potash Production Hoisting Plant Upgrade & Beyond

- Organization:
- Society for Mining, Metallurgy & Exploration
- Pages:
- 6
- File Size:
- 1259 KB
- Publication Date:
- Jan 1, 2017
Abstract
"During the mid to late 1960’s, the underground potash industry in Saskatchewan was born. For the next four decades the industry operated at a steady pace supporting a large part of the world demand; until 2008 when the potash market heightened. Operators were motivated to capitalize on this increased demand, new mines were proposed while existing mines were planning upgrades. Potash Corporation of Saskatchewan (PCS) was one of the major producers planning upgrades to their production facilities quickly, including modifying the existing headframe and shaft at the PCS Cory Site to accommodate a new 1500 tonne per hour hoisting plant. Upon completion of the project, the innovative operations group continuously reviewed methods to increase production and reduce operating costs, allowing PCS to continue being competitive on the world market. This paper will describe the design challenges encountered during the development of the infrastructure around an operating facility whilst minimizing down time, schedule, capital and construction costs. This paper will also explore the strategy to increase capacity of the newly commissioned hoisting plant. BACKGROUND Potash production is a major Saskatchewan industry, and has played a significant role in the economy for over 40 years. Production commenced in 1962 when water problems were overcome at the International Minerals and Chemical (IMC) mine near Esterhazy, Saskatchewan. A surge of development by other companies resulted in twelve companies opening ten mines by 1970. In 1975 Potash Corporation of Saskatchewan was created by the government of Saskatchewan and shortly thereafter purchased several mines in Saskatchewan, including the Cory Mine (Cory), near Saskatoon. Cory has been in operation since 1968 and is located 12 km (7.5 mi) west of Saskatoon in central Saskatchewan. The mine is located in the center of the world’s largest potash deposit, 1,000 m (3300 feet) below surface. PCS has embarked on sizable capital expansions of more than CDN $7 billion. The Cory CDN $1.6 billion expansion was expected to raise operational capability of the site to 2.7 million tonnes per year, an increase of 1.9 million tonnes per year (MTPY). To achieve 2.7 MTPY of finished product and considering the 22.6% average production recovery1, 12 MTPY of ore must be hoisted to surface for processing. To deliver this rate required upgrading of the hoisting plant to 1500 tonne per hour (TPH). To accomplish this ambitious challenge, creative thinking, careful planning and a cohesive team was needed to work together to ensure the schedule, budget and most importantly the work was completed safely"
Citation
APA:
(2017) Potash Production Hoisting Plant Upgrade & BeyondMLA: Potash Production Hoisting Plant Upgrade & Beyond. Society for Mining, Metallurgy & Exploration, 2017.