Plug Blast for a Powerhouse Intake Using an Unusual Technique

- Organization:
- International Society of Explosives Engineers
- Pages:
- 13
- File Size:
- 316 KB
- Publication Date:
- Jan 1, 2000
Abstract
The Stave Falls Project of BC Hydro, situated 65km east of Vancouver, BC, Canada, involved the construction of a new two-unit 9OMW hydro-electric facility to replace an existing powerhouse. The final phase of the intake excavation consisted of a plug blast to break the channel through into Stave Lake. The plug consisted of a rock and till wall topped with a fill cofferdam, about 51m wide and between 8 and 12m high. Total rock volume was approximately 2600m3, overlaid with about 4600m3 of till/fill. This paper describes the methodology and practical techniques used in planning and loading the blast, and the precautions taken to protect the new and existing structures and equipment. Blasting of the plug by the normal method using downholes would have required the placing of extra fill and much drilling through casing, so the contractor made the decision to drill horizontal holes from the dry, downstream side. Because of poor rock conditions, all 183 holes had to be drilled oversize at 3.5” dia. and fitted with 2.5” id. plastic pipes to keep them open. Hole lengths ranged from 2.5 to 18rn, with a pattern of 1.5m spacing and l.Om burden (with the holes slightly fanned vertically). Because of significant water exposure, a film-packaged emulsion explosive was used, placed using a pneumatic cartridge loader for maximum borehole compaction. The powder factor averaged 1.3kg/m3 (2.21bs/yd3, rock only). An initiation system of combination surface/downhole delay shocktube units was employed, with double and triple redundancy. The maximum number of holes firing in any 8ms window was limited to three (to minimize vibration), while the whole sequence was fully activated before the first hole fired. All shocktube connections were secured and covered over at the foot of the rockface before flooding the excavation downstream of the plug prior to the shot, To protect the powerhouse gates from hydraulic shock, all hole collars were grouted and an air curtain was provided. The blast was completely successful. A maximum vertical displacement of 6m was recorded, but no flyrock was evident. Readings for peak over-pressure and vibration were well below the allowed limits. Mucking proved to be easy, with fine fragmentation, full pull, and no tights.
Citation
APA:
(2000) Plug Blast for a Powerhouse Intake Using an Unusual TechniqueMLA: Plug Blast for a Powerhouse Intake Using an Unusual Technique. International Society of Explosives Engineers, 2000.