Piling Framed Tie down Concrete Retaining Wall

Deep Foundations Institute
Henry Pate Saieb Haddad
Organization:
Deep Foundations Institute
Pages:
4
File Size:
362 KB
Publication Date:
Jan 1, 2007

Abstract

"Building retaining walls in an urban area is becoming more difficult due to right-of-way restraints. Using standard concrete cantilever walls requires a construction easement behind the walls for installation, which for the most part is unavailable. To install these types of walls in a limited right-of-way requires extensive temporary walls to minimize the construction easement. Top-down construction walls utilizingtie-back anchors for support require either the purchase of the right-of-way or underground easements in the area of the anchors.These problems faced the Department on Interstate 75 widening in Knoxville, TN in an area of a large cut. A multi-story Insurance Building and a large commercial Retail Center were located at the top of the cut. To prevent any impact on the buildings, the walls had to be placed within a limited area. The option of buying the properties was prohibitively expensive. Due to the height of the two walls and the variability of the underling rock line, contiguous caisson pile cantilever walls were contemplated as the only wall type that would be appropriate. The cost of the two walls was estimated to be very close or even higher than the cost of purchasing the two buildings. The Department believed that there must be a better way to deal with the problem. A vertically tied-down pile frame wall constructed from the top-down with a concrete facing was developed. This allowed the construction of the walls to be restricted to the available limited area and provided substantial savings for the State.INTRODUCTIONThe widening of I-40/75 has been a major transportation project in the Knoxville area which is being constructed by the Tennessee Department of Transportation. The project includes 18 Retaining Walls and 13 Bridges.Two of the 18 Retaining Walls, refer to Figure 1, are to support two valuable properties, one being an insurance company housed in a multi-story office building and the other a suburban shopping center which were appraised at $13.0 million and $5.0 million respectively. Due to the 31 ft. (9.5m) maximum height of each of the two Retaining Walls and the limited Right-of- Way of 15.0 feet (4.6m), a contiguous caisson pile cantilever wall was proposed for each of the two retaining wall sites with an estimated cost of $12.0 million each. The contiguous pile cantilever Wall is comprised of a line of caisson piles socketed into underlying competent bedrock. The design required that 4 ft. (1219mm) dia. piles be installed at 6 ft. (1.83m) centers, socketed into rock in order to provide lateral stability and restrict lateral wall movement to acceptable limits. The line of caissons would be fronted with a cast-in-place concrete face wall"
Citation

APA: Henry Pate Saieb Haddad  (2007)  Piling Framed Tie down Concrete Retaining Wall

MLA: Henry Pate Saieb Haddad Piling Framed Tie down Concrete Retaining Wall. Deep Foundations Institute, 2007.

Export
Purchase this Article for $25.00

Create a Guest account to purchase this file
- or -
Log in to your existing Guest account