Papers - Drilling and Blasting - Electric Blasting Practices of the Tennessee Copper Company (Mining Technology, Sept. 1942.) (with discussion)

- Organization:
- The American Institute of Mining, Metallurgical, and Petroleum Engineers
- Pages:
- 10
- File Size:
- 643 KB
- Publication Date:
- Jan 1, 1943
Abstract
The mines of The Tennessee Copper Co. are in the Ducktown Basin, in southeastern Tennessee. The ore is a heavy sulphide consisting principally of chalcopyrite, pyrite and pyrrhotite and in places running as high as 95 per cent sulphur and iron. Operating mines are the Burra Burra and Eureka. Development ' of the Boyd ore body was started in 1940. Late in 1939 the decision was made to change from fuse and cap to all electric blasting and at the same time electric cap lamps were installed to replace carbide. These changes were made to improve the safety and working conditions in the mines. Both the Bureau of Mines and explosives manufacturers recommended electric blasting as a safety measure. Until that rime, electric blasting had been used only for shaft sinking and in places where it was absolutely essential for safety. Very few men had had experience in this type of blasting, as the places where it was required were those that also required direct supervision. It was necessary for the mining staff to work out methods, procedure, and equipment to be used. In this they were ably assisted by representatives of the explosives manufacturers. Many mistakes were made and it is the purpose of this paper to describe the original plan and installation, show the major difficulties encountered. the remedies applied, and present the practices now being followed. Comparison of costs of the two methods will also be discussed. About six months were required to make the change and eliminate fuse and cap blasting entirely. The first electric blasting stations were installed in November 1939 and the last fuse was taken underground in May 1940. A very unusual condition forced the use of fuse for a short time in one heading after May, but that will be discussed later. Original Equipment and Installation A power line is generally recommended as a source of current where permanent blasting stations are used. The plan worked out for electric blasting was to tap 220-volt alternating-current lines when they were available and use 250-volt direct current from the trolley wire at all other places. A blasting machine would be available at each shaft for places where there were no regular blasting stations and could be used if a regular station should fail. The equipment decided on was No. 16 duplex reinforced lamp cord for lines to within about 50 ft. of the working place and No. 20 lead wire from that point to the shots. An open double-pole, double-throw switch with slate base was put in the circuit, so connected that the down position would close the line to the shots 2nd the up position would connect it to the Iine from the power contactor. This switch was located in the circuit as close to the blast as was safe (should the shots explode when it was placed in the shooting
Citation
APA:
(1943) Papers - Drilling and Blasting - Electric Blasting Practices of the Tennessee Copper Company (Mining Technology, Sept. 1942.) (with discussion)MLA: Papers - Drilling and Blasting - Electric Blasting Practices of the Tennessee Copper Company (Mining Technology, Sept. 1942.) (with discussion). The American Institute of Mining, Metallurgical, and Petroleum Engineers, 1943.