Abstract
"Yara Siilinjärvi in Finland is the Western Europe's only apatite mine. Annually it produces one million tons of apatite concentrate, which creates 10 million tons of tailings. At the beginning of 2017, Yara replaced their conventional TSF with a new tailings treatment plant, which increased the solids content of the slurry from 45–48% to 66–68%, making it possible to deposit as a paste. This extended the life-span of the current TSF from 2020 to 2035. This paper presents the storyline of the Yara paste plant project. The project began with laboratory testing and then progressed to pilot-scale thickening and beaching trials. After successful pilot trials, the final process design was implemented. Process automation played a key role in the project. An advanced control system is needed to maintain process stability and the desired operation point in various operational circumstances. Since commissioning the paste plant has been running consistently with an underflow solids content of 66-68%, with average beach slope angles of 3.5 degrees in the tailings disposal area. Robust thickener operation also leads to the trouble-free high-density pumping and high availability of the plan. During first year of operation the plant’s availability has been very good, over 97%, and currently, the plant is operated remotely from the main concentrator plant.INTRODUCTION The Yara Siilinjärvi Plant is owned by Yara International, a Norwegian fertiliser company. Yara Siilinjärvi is Western Europe's only apatite mine, and it primarily produces apatite concentrate for its Siilinjärvi phosphoric acid plant. A portion of the concentrate is also dried and shipped to other Yara fertiliser plants. The site annually produces one million tons of apatite concentrate, which creates approximately 10 million tons of tailings. Extending the lifespan of the 1150-hectare tailings storage facility has been studied in Siilinjärvi for a long time. The aim has been to use the same tailings area footprint, without any new land purchases or major dam increases. An important part of the process has been to study the possibilities for using new technologies, especially thickened tailings technology (Ruhanen, 2014)."
Citation
APA: (2019) Optimising the Operation of Paste Thickening at the Yara Siilinjärvi Plant (8a3674cf-2785-43be-b17f-05be124f63bf)
MLA: Optimising the Operation of Paste Thickening at the Yara Siilinjärvi Plant (8a3674cf-2785-43be-b17f-05be124f63bf). Canadian Institute of Mining, Metallurgy and Petroleum, 2019.