Numerical Evaluation and Optimization of Grout Backfill Strategy for a Subsurface Gas Tunnel

- Organization:
- Society for Mining, Metallurgy & Exploration
- Pages:
- 10
- File Size:
- 1106 KB
- Publication Date:
- Jan 1, 2016
Abstract
"Grout backfill strategy for a particular subsurface concrete tunnel (~4.9km long, 3.5m in diameter, carrying 20” gas pipeline) was based on achieving 1:100 slope of the fill in order to progressively fill the tunnel, in a series of 350m section. Grout rheology, particularly its non-Newtonian and thixotropic behavior, determines the final fill slope for given backfill strategy. The objective of this study was to simulate the two-phase grout mix backfill process using Computational Fluid Dynamics (CFD) and determine the slope of the fill to validate and optimize the backfill strategy. Three dimensional CFD study showed that for a 500m long tunnel section with a single injection point of grout, given its rheology, it will likely keep flowing without filling the 500m section height wise. Design optimization for filling was carried out using two dimensional studies to make the backfill process “slope independent” by incorporating a 2.5m high bulkhead at ~1,000m. INTRODUCTION As part of a gas field development a 20” onshore gas pipeline is required from the landfall site to the processing terminal some 8km inland. At the landfall site the gas pipeline is routed in a ~5km underground tunnel underneath a bay. For operational reasons and planning consents as well as to mitigate environmental impact based on an environmental impact study, once the gas pipeline and the associated services and spares have been installed, the subsurface gas tunnel will be fully grouted. There will be no permanent access to the tunnel after construction is completed and the site compounds have been reinstated once works are complete. One of the key requirements is that “full grouting of the tunnel” is desired. The grouting material used is a non-Newtonian and thixotropic fluid mixture of bentonite, cement, plasticizer, retarder/stabilizer and water. The tunnel is filled progressively in 350m sections using a combination of existing and new pipework assuming the grout rheology will yield a fill slope of 1:100 in a 350m section. The proposed grouting system used one pump at the grouting compound to pump the grout into the tunnel using the existing tunneling pipework. For the longer runs a second booster pump was used in series to pump the grout to its final discharge location. The filling process is controlled via a system of flow meters, pressure transmitters and a tunnel CCTV system."
Citation
APA:
(2016) Numerical Evaluation and Optimization of Grout Backfill Strategy for a Subsurface Gas TunnelMLA: Numerical Evaluation and Optimization of Grout Backfill Strategy for a Subsurface Gas Tunnel. Society for Mining, Metallurgy & Exploration, 2016.