Minerals Beneficiation - Handling and Drying of Wet Ambrosia Lake Ores

- Organization:
- The American Institute of Mining, Metallurgical, and Petroleum Engineers
- Pages:
- 3
- File Size:
- 817 KB
- Publication Date:
- Jan 1, 1961
Abstract
Since the ore mined in the Grants-Ambrosia Lake uranium area is taken from a water-saturated sandstone formation, part of the milling operation includes a drying process. The authors discuss the merits and disadvantages of two methods: natural drying and mechanical gas-fired drying; operating and cost data are included. In the Grants-Ambrosia Lake uranium area, approximately 7000 tons of ore are mined each day from a water-saturated sandstone formation. This ore is sampled and treated at four separate milling operations. Prior to the design and initial construction of the milling facilities, very little was known as to the physical properties of the ore which would be handled in the sampling and crushing facilities at the mills. All four mills initially were constructed without ore-drying facilities. As mining proceeded, it was determined that, even after drying the ore in place by use of drainage development underground, the moisture content of the ore as hoisted averaged approximately 18 pct. Actually, some of the mines produced ores which resembled cream-of-wheat in character and had a moisture content in excess of 24 pct. Each of the four mills had a differently designed sampling and crushing plant; therefore, the moisture content of the ores had varying adverse effects upon the operation of the plants. It was determined after some experience that most of the sampling and crushing facilities could not economically handle ore if the moisture content was greater than 10 pct—one operator considers 12 pct moisture as a maximum. In all of the plants, moisture content over 8 pct increases costs to some extent. In addition to the added sampling and crushing costs, some of the mills were located 15 to 20 miles from the mines and the high moisture content of the ores increased the haulage costs from the mine to the mill. It was generally conceded that it was necessary to employ some method to reduce the moisture content of the ore prior to sampling. Several methods were considered: 1) natural drying at the mine site, 2) mechanical gas-fired drying at the mill site, 3) mechanical gas-fired drying at the mine site, 4) radiant heating on concrete clabs, and 5) infrared shed drying. After preliminary investigation all possibilities but natural drying and mechanical gas-fired drying at the mill site were eliminated. NATURAL DRYING A cooperative feasibility study was conducted on the natural drying method. This study indicated the following: 1) During summer months May through September, ore piled 4-ft deep would dry from +20 to +10 pct HzO in 30 days with no mechanical turning. 2) In the first four days after piling a reduction of 5 to 7 pct total moisture content was accomplished by drainage and absorption of the water into the underlying ground on which the ore was piled, providing the ground surface absorption rates approached 10 gal per sq ft per day. After the first four days the decrease of moisture caused by drainage was practically nonexistent. 3) In the summer months drying by evaporation amounted to approximately 0.1 pct decrease in total moisture per day and mechanical turning of the ore could increase this as much as three times. 4) Climatic conditions of the area indicated that: a) Air temperatures averaged 64' May, June, July, August, September; 41" October, November, December, March, April; 31" January, February. b) Average rain fall was 10 in. with 40 pct of this occurring during July and August. c) Only on very rare occasions were there over five consecutive days with below freezing temperatures. d) The annual evaporation rate was approximately 75 in. On the basis of this study, two of the mill operations decided to attempt to meet the moisture specifications by natural drying supplemented by mechanical turning. The other two operations decided upon rotary gas-fired drying at the mill site. The natural drying method has been quite successful in practice. The ore running approximately 18 pct moisture is trucked from the head frame and piled in rows about 6 ft wide, 3 1/2 ft deep, 5 feet apart during the months of May through September. In approximately 30 days this ore will
Citation
APA:
(1961) Minerals Beneficiation - Handling and Drying of Wet Ambrosia Lake OresMLA: Minerals Beneficiation - Handling and Drying of Wet Ambrosia Lake Ores. The American Institute of Mining, Metallurgical, and Petroleum Engineers, 1961.