Management of Obstructions and Adverse Ground Conditions: SCL Tunnel Works on Crossrail C300/410

Society for Mining, Metallurgy & Exploration
Olivia Perkins Adrian St. John Shawn Sismondi Vicky Potts
Organization:
Society for Mining, Metallurgy & Exploration
Pages:
10
File Size:
1094 KB
Publication Date:
Jan 1, 2016

Abstract

"INTRODUCTION An inherent aspect of any tunnelling project is ground risk: how it is identified, quantified and managed throughout the various stages of a project. Early identification of these risks, such as adverse ground conditions or potential obstructions is crucial; however specific identification of all risks will inevitably be limited by the extent of the desk study, ground investigation and accuracy of as-built information available, particularly in a densely populated urban environment such as London with a long and varied history of development. It is therefore crucial to have suitable plans and procedures in place for dealing with potential ground risk scenarios if they occur during construction work to ensure the safety of the workforce and to protect nearby critical assets. A number of experiences of potential ground risk were encountered during the Sprayed Concrete Lining (SCL) works on Crossrail contract C300/410 which was constructed by a joint venture of BAM Ferrovial Kier (BFK). The C300/410 works, undertaken in the heart of London, comprised of over 2.5km of SCL tunnels for Bond Street and Tottenham Court Road Stations and the Fisher Street crossover, as well as two 6.2km TBM tunnel drives between Royal Oak and Farringdon. BFK appointed Donaldson Associates as their SCL designers for the works; together they were responsible for excavation stability up to the point of ring closure. Despite the majority of SCL tunnelling works at Bond Street and Tottenham Court Road being through the favourable medium of London clay, there remained areas of local geotechnical challenges. Some of these were expected from the outset, some became apparent as works progressed from records of other nearby excavation works, and some were only encountered during tunnel excavation. Being located in the centre of London meant that there always remained a possibility of meeting some form of obstruction from previous structures. However, identification of all potential issues prior to the commencement of the works was challenging and proved to not be entirely possible. Through a series of case studies, this paper documents incidents where obstructions or adverse ground conditions arose. These scenarios all had the potential to cause safety risks, impact the tunnel design and/or construction methods and ultimately add time and cost to the works. The paper discusses how these challenges were overcome which utilised in part, a progressive risk reduction cycle, feeding back knowledge gained at all stages of construction into the approach for undertaking the works. It also examines what could be done in future to further reduce the ground risk through early identification, communication, education and appropriate contingency measures."
Citation

APA: Olivia Perkins Adrian St. John Shawn Sismondi Vicky Potts  (2016)  Management of Obstructions and Adverse Ground Conditions: SCL Tunnel Works on Crossrail C300/410

MLA: Olivia Perkins Adrian St. John Shawn Sismondi Vicky Potts Management of Obstructions and Adverse Ground Conditions: SCL Tunnel Works on Crossrail C300/410. Society for Mining, Metallurgy & Exploration, 2016.

Export
Purchase this Article for $25.00

Create a Guest account to purchase this file
- or -
Log in to your existing Guest account