Longwall Development Problems

- Organization:
- The American Institute of Mining, Metallurgical, and Petroleum Engineers
- Pages:
- 5
- File Size:
- 205 KB
- Publication Date:
- Jan 1, 1981
Abstract
Keeping development ahead of retreat mining is a problem which occurs nearly everywhere longwall mining is used in the United States. As improved equipment technology has allowed the application of longwall mining to more difficult mining conditions, and with higher retreat rates, the problem has become more critical. Many factors determine development speed, including roof and floor conditions, mining heights, seam heights, and the number of entries. In an effort to maximize the rate of development and production from development sections, U. S. Steel's Gary District has used five entry, three entry, four entry and is planning two entry development panels at its different mines. With the introduction of various types of shield supports, it is now possible to utilize longwall mining in higher coal over 3 meters (10 feet), lower coal under one meter, in difficult roof conditions, and with soft floor. Improved shearers of 300 KW (400 HP) and more make cutting heights over 3 meters (10 feet) possible, and off pan shearers and improved Gleithobel plows make cutting less than 1 meter (40 inches) seam height possible. Longwall mining under these conditions puts an added strain on the ability to develop panels as fast as they are retreated. Poor roof conditions require a substantial amount of additional roof support to ensure that roof control in the head and tall entries will not hinder longwall retreat. The additional measures of longer bolts, resin bolts, point anchor resin bolts, roof mats, roof trusses, steel or wood cross bars, and roof grouting all place an additional burden on man power, installation time, and cost on the mining cycle. Additional roof bolting on development can cut the potential mining rate in half, and any roof falls cause significant delays to mining. Timbers and cribs can restrict ventilation and require more entries. Soft floor conditions can greatly impede development through tramming difficulties with shuttle cars and roof bolters, time required for cleaning and repairing roadways, and maintenance difficulties on equipment. High coal sometimes requires rib support to be Installed during the mining cycle, further cutting the mining rate. Mining low seams requires that roof or floor be mined in the head and tail entries as well as the track or tractor roadway entry to provide clearance of the longwall equipment. Mining this rock slows down the mining rate because of the extra material being mined and the extra wear and tear on equipment. To a large degree these conditions effecting development speed cannot be controlled.
Citation
APA:
(1981) Longwall Development ProblemsMLA: Longwall Development Problems. The American Institute of Mining, Metallurgical, and Petroleum Engineers, 1981.