Instrumented Hybrid Shoring System for a Deep Temporary Excavation Incorporating Cutter Soil Mixing in Vancouver, BC, Canada

Deep Foundations Institute
Marina S. W. Li Nadir Ansari Brian W. Wilson
Organization:
Deep Foundations Institute
Pages:
12
File Size:
808 KB
Publication Date:
Jan 1, 2017

Abstract

"A hybrid shoring system consisting of cast-in-place soldier piles with Cutter Soil Mixing (CSM) infill panels was constructed for temporary support of a 19.8 m (65 ft) deep excavation in Vancouver, British Columbia, Canada. Deep Mixing (DM) was completed up to 9.7 m (32 ft) in fill, peat, wood waste and clayey silt with embedment in dense till, and soldier piles constructed through the dense till extending to below final excavation level. Two trial CSM panels were installed ahead of production to assist with developing the termination criteria of the CSM panels in the dense till. The constructed depth of the CSM panels was based on interpretation of real-time monitoring data obtained through the Bauer B-tronic system. Inclinometer monitoring data from two CSM panels and two soldier piles, as well as soldier pile survey target data was used to assess and monitor the performance of the hybrid shoring system throughout bulk excavation. The objectives of this paper are to provide an overview of the design and construction aspects of the hybrid DM shoring system and to present inclinometer and pile target data to demonstrate the lateral performance of the CSM infill panels and soldier piles. This paper also discusses the merits of using real-time monitoring data as part of the engineering decision-making process for validating CSM panel construction. BACKGROUND A hybrid DM shoring design was recently completed for a high-rise development in downtown Vancouver, British Columbia for temporary support of a five level basement excavation. Deep mixing was proposed by the excavation and shoring design-build team as the preferred method to construct infill panels between soldier piles because of the speed at which the shoring system could be constructed in variable fill, peat, wood waste and overburden compared with traditional secant piling methods. The development site is generally a truncated triangle in plan, with the longest side of the triangle being approximately 115.7 m (380 ft) long and the two shorter sides being approximately 71.6 m (235 ft) (Hybrid Shoring Wall 1) to 75.0 m (246 ft) (Hybrid Shoring Wall 2) long. The site is bounded by an existing bridge off-ramp structure along its longest side, and by city streets on the other two sides, as shown in Figure 1. The truncated section is approximately 16.8 m (55 ft) (Hybrid Shoring Wall 3) long. Due to project constraints, the hybrid DM and soldier pile shoring system was only proposed for the two shorter sides of the triangle and the truncated section. Traditional secant piles were installed for the longest side. This paper focusses on the hybrid shoring system. A typical detail showing the CSM infill panel with the soldier piles is presented in Figure 2."
Citation

APA: Marina S. W. Li Nadir Ansari Brian W. Wilson  (2017)  Instrumented Hybrid Shoring System for a Deep Temporary Excavation Incorporating Cutter Soil Mixing in Vancouver, BC, Canada

MLA: Marina S. W. Li Nadir Ansari Brian W. Wilson Instrumented Hybrid Shoring System for a Deep Temporary Excavation Incorporating Cutter Soil Mixing in Vancouver, BC, Canada. Deep Foundations Institute, 2017.

Export
Purchase this Article for $25.00

Create a Guest account to purchase this file
- or -
Log in to your existing Guest account