Abstract
The DC Water and Sewer Authority's Long Term Control Plan includes tunnels, sewer separation, pumping station rehabilitation and green infrastructure to reduce combined sewer overflow (CSO) discharges to the District waterways.
The Northeast Boundary Tunnel is a deep, large sewer tunnel that will reduce CSO discharges; signifi- cantly mitigate known chronic flooding in the Northeast Boundary drainage area and improve the water quality of the Anacostia River.
This paper presents the unique combination of Owner and Contractor perspectives of the entire Project from conception through procurement, execution, and contract management, providing lesson learned, chal- lenges encountered, and solutions implemented to deliver the Project successfully.
Citation
APA:
(2024) From Planning to Commissioning: A Complete Overview of the Northeast Boundary Tunnel Project - NAT2024MLA: From Planning to Commissioning: A Complete Overview of the Northeast Boundary Tunnel Project - NAT2024. Society for Mining, Metallurgy & Exploration, 2024.