Foundation Challenges And Innovative Solutions: The Wharf Phase 2, Washington, Dc

Deep Foundations Institute
Aaron L. Sacks Joseph K. Carey David R. Good Srinivas Yennamanda
Organization:
Deep Foundations Institute
Pages:
10
File Size:
1683 KB
Publication Date:
Oct 1, 2022

Abstract

Construction of Parcels 6 and 7, the second phase of The Wharf, began in 2019 and geotechnical construction was completed by December 2020. The overall project consisted of horizontal site, parks, and office buildings. The Wharf’s Phase 2 development includes approximately 1.2 million ft2 (110,000 m2) of above-grade construction including five multi-story, mixed-use buildings constructed over up to three levels of underground parking. The site is located between the WMATA Green Line Tunnels to the north and the Washington Channel to the south; it is bisected by a 108-in. (2740-mm) diameter DC Water outfall pipe. This arrangement, along with very difficult ground conditions, created challenges in the geotechnical design and construction. The support of excavation for this complex project required several different methodologies, including sheet piles, soldier piles, displacement piles, tiebacks, deep foundation anchors, jet grouting, and internal bracing with multi-tier rakers. Ground improvement was also required for support of spread footings in soft soils over the garage footprint. Underpinning of the active 108-in. (2740-mm) diameter DC Water outfall pipe running on a north/south alignment through the center of the site between the two garage structures was also performed. Since portions of the support of excavation are below the groundwater table, an extensive pre-excavation dewatering program was necessary and was separate from the foundation package. On the north side of the project, support of excavation (SOE) was required on a curved alignment, offset approximately 10 ft (3 m) from the outbound Green Line tunnel. Due to the proximity of the tunnel, a stiff, near-zero displacement wall was required. A portion of the buildings extend over the tunnels, imparting load to the tunnels to approximately restore original overburden loads excavated for the basement space. The building foundation is a 3 to 4-ft (0.9 to 1.2-m) thick mat slab anchored into the Potomac clay formation. Continuous movement monitoring of the tunnels was performed by an automated system. This paper describes the design and construction of the SOE and foundations for this high-profile project, which required collaboration between the Owner, Engineer, Construction Manager, and Specialty Geotechnical Contractor to solve many challenges.
Citation

APA: Aaron L. Sacks Joseph K. Carey David R. Good Srinivas Yennamanda  (2022)  Foundation Challenges And Innovative Solutions: The Wharf Phase 2, Washington, Dc

MLA: Aaron L. Sacks Joseph K. Carey David R. Good Srinivas Yennamanda Foundation Challenges And Innovative Solutions: The Wharf Phase 2, Washington, Dc. Deep Foundations Institute, 2022.

Export
Purchase this Article for $25.00

Create a Guest account to purchase this file
- or -
Log in to your existing Guest account