Foundation Challenges And Innovative Solutions: The Wharf Phase 2, Washington, Dc

- Organization:
- Deep Foundations Institute
- Pages:
- 10
- File Size:
- 1683 KB
- Publication Date:
- Oct 1, 2022
Abstract
Construction of Parcels 6 and 7, the second phase of The Wharf, began in 2019 and geotechnical
construction was completed by December 2020. The overall project consisted of horizontal site, parks,
and office buildings. The Wharf’s Phase 2 development includes approximately 1.2 million ft2 (110,000
m2) of above-grade construction including five multi-story, mixed-use buildings constructed over up to
three levels of underground parking. The site is located between the WMATA Green Line Tunnels to the
north and the Washington Channel to the south; it is bisected by a 108-in. (2740-mm) diameter DC Water
outfall pipe. This arrangement, along with very difficult ground conditions, created challenges in the
geotechnical design and construction. The support of excavation for this complex project required several
different methodologies, including sheet piles, soldier piles, displacement piles, tiebacks, deep foundation
anchors, jet grouting, and internal bracing with multi-tier rakers. Ground improvement was also required
for support of spread footings in soft soils over the garage footprint. Underpinning of the active 108-in.
(2740-mm) diameter DC Water outfall pipe running on a north/south alignment through the center of the
site between the two garage structures was also performed. Since portions of the support of excavation are
below the groundwater table, an extensive pre-excavation dewatering program was necessary and was
separate from the foundation package. On the north side of the project, support of excavation (SOE) was
required on a curved alignment, offset approximately 10 ft (3 m) from the outbound Green Line tunnel.
Due to the proximity of the tunnel, a stiff, near-zero displacement wall was required. A portion of the
buildings extend over the tunnels, imparting load to the tunnels to approximately restore original
overburden loads excavated for the basement space. The building foundation is a 3 to 4-ft (0.9 to 1.2-m)
thick mat slab anchored into the Potomac clay formation. Continuous movement monitoring of the
tunnels was performed by an automated system. This paper describes the design and construction of the
SOE and foundations for this high-profile project, which required collaboration between the Owner,
Engineer, Construction Manager, and Specialty Geotechnical Contractor to solve many challenges.
Citation
APA:
(2022) Foundation Challenges And Innovative Solutions: The Wharf Phase 2, Washington, DcMLA: Foundation Challenges And Innovative Solutions: The Wharf Phase 2, Washington, Dc. Deep Foundations Institute, 2022.