Eagle Mine and Mill Commissioning

- Organization:
- Canadian Institute of Mining, Metallurgy and Petroleum
- Pages:
- 15
- File Size:
- 3139 KB
- Publication Date:
- Jan 1, 2015
Abstract
In July of 2013, Lundin Mining acquired the 2,000 tpd Eagle nickel and copper project from Rio Tinto. The project had been put on hold earlier in the year and construction was approximately 50% complete. Lundin immediately accelerated project activities and by September of 2014 the project was constructed, commissioned and ramping up. The newly commissioned facilities went on to reach design throughput, recovery and product quality targets by the end of the year. This was accomplished ahead of schedule and below budget despite numerous obstacles including the worst winter on record in the past 50 years for the area. What led to the success of the project, and in particular the commissioning phase of the project? This paper takes a high level look back and provides an overview of the methodology used, key issues encountered and lessons learned to answer this question.
Citation
APA:
(2015) Eagle Mine and Mill CommissioningMLA: Eagle Mine and Mill Commissioning. Canadian Institute of Mining, Metallurgy and Petroleum, 2015.