Dynamic and Static Load Tests on Tapered Piles in Soils Exhibiting Time-Dependent Capacity Gain

Deep Foundations Institute
Terrence M. Carroll Chu E. Ho
Organization:
Deep Foundations Institute
Pages:
9
File Size:
1298 KB
Publication Date:
Jan 1, 2015

Abstract

"A pile installation and load testing program on driven tapered piles was undertaken at John F. Kennedy International Airport in New York City for the extension of the existing Terminal 4. As part of the program, dynamic testing by means of the Pile Driving Analyzer (PDA) was performed on several preliminary test piles as well as production piles. The results of the dynamic tests and subsequent static load tests were reviewed to develop an understanding of the pile-soil response of a tapered pile during driving and after setup. Pile setup occurred as a result of increase in shaft resistance with virtually no increase in toe resistance. More than 150 tons of additional capacity was gained after the setup time.The capacities measured during driving from the PDA are typically used as the basis for determining the pile driving set criteria, with the required initial driving capacities determined largely by the contractor’s experience. An improved appreciation of the setup phenomenon is required to better refine the driving criteria at the end of initial driving such that the required ultimate capacities can be obtained, with reasonable confidence, after a period of setup.This paper presents interpretation of pile-soil behavior from Case Pile Wave Analysis Program (CAPWAP) analyses and discusses the mechanism of increased capacity as a result of setup effects. Time-dependent capacity gain as a result of setup effects should be based on the extrapolation of the shaft resistance component rather than the total pile capacity as is commonly practiced. Prediction of pile performance using this approach was in good agreement with observed static and dynamic load test results.IntroductionTapered piles have been adopted for various projects at John F. Kennedy International Airport (JFKIA) since the late 1940’s. Initially timber piles were used exclusively, with steel Monotube piles being used from at least the 1980’s (Horvath and Trochalides, 2004). The steel Tapertube pile was developed in the mid-1990’s and has commonly been used in recent construction (Brusey and Yin, 2008). The Tapertube piles used for this project consisted of a 25 foot long tapered section that was 8 inches in diameter at the tip and 18 inches in diameter at the top. An 18 inch diameter straight pipe was welded above the tapered section."
Citation

APA: Terrence M. Carroll Chu E. Ho  (2015)  Dynamic and Static Load Tests on Tapered Piles in Soils Exhibiting Time-Dependent Capacity Gain

MLA: Terrence M. Carroll Chu E. Ho Dynamic and Static Load Tests on Tapered Piles in Soils Exhibiting Time-Dependent Capacity Gain. Deep Foundations Institute, 2015.