DSU TBM for Vishnugad Pipalkoti - TBM Design Development for Large Diameter Rock Tunnels under the High Covers of the Himalaya

- Organization:
- Society for Mining, Metallurgy & Exploration
- Pages:
- 10
- File Size:
- 4024 KB
- Publication Date:
- Jan 1, 2016
Abstract
"INTRODUCTIONDouble Shield TBMs were introduced in the market in the early seventies with three main targets:• Increase the TBM performances in term of advance per day thanks to the ability to erect a segmental lining simultaneously with the excavation phase.• Be able to advance through unstable and disturbed rocks under the protection of the shields• Provide a finished tunnel by installing a precast lining as the TBM advance.In 2003 SELI developed the design of the Double Shield Universal (DSU) TBM as an evolution of the original Double Shield TBM design.This new TBM design was targeted to improve: the TBM capability to advance through squeezing/converging rock formations under high cover, the telescopic joint design (allowing by such to operate the machine in double shield mode in very weak rock), the capability of the TBM to investigate and treat the ground around and ahead of the tunnel face.In the same lapse of time Single Shield TBMs, originally utilized for soft ground tunnelling, extended progressively their range of application to mix rocks and finally to hard rock tunnelling with increasing performances.This also thanks to the substantial reduction in the installation time of the segmental lining ring that contributed to minimize the TBM stand by time between two consecutive boring strokes.Today the choice between the two types of TBMs needs to be carefully evaluated project by project since one type of TBM may “prevail” in certain geologies and diameters and vice versa.THE VISHNUGAD PIPALKOTI TUNNELThe Vishnugad Pipalkoti Tunnel is part of the 444 MW Vishnugad Pipalkoti Hydro Electric Project (VPHEP) on Alaknanda river in Uttarakhand (India).The Owner is the Indian electric company “Tehry Hydro Development Corporation” (THDC) and the World Bank finances the project.The Headrace Tunnel total length is 13.4 Km and a section of about 12,3km will be excavated by TBM by SELI Overseas (Italy) in subcontract to HCC (India) the General Contractor for the project. The TBM will be delivered ex workshop in March 2016 and it is foreseen to start boring in the second half of 2016.Figure 1 below shows the location of the project and the following Table 1 summarizes the geometrical characteristics of the TBM tunnel."
Citation
APA:
(2016) DSU TBM for Vishnugad Pipalkoti - TBM Design Development for Large Diameter Rock Tunnels under the High Covers of the HimalayaMLA: DSU TBM for Vishnugad Pipalkoti - TBM Design Development for Large Diameter Rock Tunnels under the High Covers of the Himalaya. Society for Mining, Metallurgy & Exploration, 2016.