Diaphragm Walls for Seepage Control and Remediation: Three Case Histories

- Organization:
- Deep Foundations Institute
- Pages:
- 12
- File Size:
- 2005 KB
- Publication Date:
- Jan 1, 2016
Abstract
"This paper presents the utilization of slurry walls methods for the recent remediation of three high hazard active dams in the United States. Tuttle Creek Dam, located in Manhattan, KS, required seismic retrofit. To this extent, transverse shear walls were installed on the downstream slope using self-hardening slurry (SHS) to reinforce the liquefiable foundation soils. Herbert Hoover Dike, located around Lake Okeechobee, FL, is subject to potential failure because of internal erosion, piping and slope instability at high water levels. The innovative use of the hydromill equipment with SHS allowed the successful construction of the cutoff wall through heterogeneous soils and rock. At Bolivar Dam, located in Bolivar, OH, under-seepage negatively affects the structural stability of the dam, and a partial seepage barrier wall is required through the upstream slope of the dam. In this case, the Contractor selected the plastic concrete seepage barrier, excavated by a combination of clamshell and hydromill equipment. The main features of the three projects are summarized in Table 1. IntroductionTuttle Creek Dam was constructed by the U.S. Army Corp of Engineers (USACE) on the Big Blue River in North-East Kansas in the 1950s for flood control. Tuttle Creek Dam is a zoned earthfill embankment, 7,500 ft long and about 137 ft high with a crest width of 50 ft (Fig. 1). It is located in an area of moderate seismicity associated with an old continental rift zone located just to the east of the dam. The USACE, under the Dam Safety and Assurance Program, determined the need for remediation. Site investigations and geotechnical analyses identified the upper alluvial foundation sands as being susceptible to liquefaction when subjected to the Maximum Credible Earthquake.In 2005, USACE awarded a construction-manager-at-risk/early Contractor involvement contract. The USACE and the Contractor closely cooperated to identify the most effective technologies, materials and configurations to be used in the remediation. The original remediation design required both the upstream and downstream slope stabilization of liquefiable foundation. Results of refined seismic deformation analyses revealed that the stabilization of the downstream slope and toe was needed to protect the downstream seepage control system and to provide assurance that a liquefaction-induced flow slide would not occur (Stark et al., 2012)."
Citation
APA:
(2016) Diaphragm Walls for Seepage Control and Remediation: Three Case HistoriesMLA: Diaphragm Walls for Seepage Control and Remediation: Three Case Histories. Deep Foundations Institute, 2016.