Diaphragm Wall Construction, Instrumentation, and Testing for a Hydroelectric Power Facility

Deep Foundations Institute
Jeff A. Segar Nicolas A. Willig-Friedrich David Gatto
Organization:
Deep Foundations Institute
Pages:
12
File Size:
1904 KB
Publication Date:
Jan 1, 2016

Abstract

"With the increasing demand for electricity, and requirements to generate this power cleanly, more producers are turning towards hydroelectric power. A project in Iowa currently under construction will retrofit an existing Army Corps of Engineers Dam with a hydroelectric generating facility. The design of the intake structure requires the construction of a diaphragm retaining wall. The T-shaped diaphragm wall elements retain an unbalanced fill height up to 21.3 meters (70 feet). The design required a single production element be constructed, tested, and instrumented prior to beginning construction of the rest of the elements. The testing included extensive concrete mix design development, coring, and Cross Hole Sonic Logging. Installed in the other production elements are 10 inclinometers, 4 pressure cells, 4 piezometers, and multiple survey monuments. Some of these instruments require manual readings while most are monitored by an automatic data acquisition system and instantly transferred to a website providing real-time graphical display of the data. This paper will discuss the construction of the diaphragm wall from the contractor’s perspective when working on a site only large enough for two service cranes and a Hydromill excavation unit, without any storage area on the construction pad, describe the testing performed and the quality control procedures employed, and investigate the information gained from the automated instruments providing real time measurement readings.INTRODUCTIONIn 1964 the US Army Corps of Engineers (USACE) constructed a dam by raising the surface grade approximately 34.7 meters (114 feet) above the natural ground line using a combination of fill types. This earthen dam stretched slightly longer than a mile intersecting the flow of the existing Des Moines River. The center of the dam is a concrete spillway consisting of 12 monolith sections. On each end, three of the sections extend 42.6 meters (140 feet) from the spillway to transition from the concrete dam sections to the earthen dam section. Adjacent to these three sections on the East end is where the contractor is actively working, for a private developer under a lease agreement with USACE, on this site to convert it to a Hydroelectric facility licensed for an output of 36.4 megawatts, enough power to meet the needs of about 18,000 homes. To create this, a powerhouse structure, housing two vertical Kaplan turbines is being added to the downstream side of the existing dam. From the power house, two penstock pipes will be cored through the existing concrete monolith sections and connect to the Intake structure on the upstream side of the dam. Protecting and reinforcing the dam adjacent to the intake structure is a new diaphragm wall. This wall is constructed using T-shaped diaphragm elements, acting as a cantilever retaining wall for the intake platform. Figure 1 shows a diagram of the upstream features of the construction."
Citation

APA: Jeff A. Segar Nicolas A. Willig-Friedrich David Gatto  (2016)  Diaphragm Wall Construction, Instrumentation, and Testing for a Hydroelectric Power Facility

MLA: Jeff A. Segar Nicolas A. Willig-Friedrich David Gatto Diaphragm Wall Construction, Instrumentation, and Testing for a Hydroelectric Power Facility. Deep Foundations Institute, 2016.

Export
Purchase this Article for $25.00

Create a Guest account to purchase this file
- or -
Log in to your existing Guest account