Design Of Cost-Effective Retaining Wall At The Junction Of Approach Bridge Over A Ramp

Deep Foundations Institute
Biswajit Das Dr. Anup Kumar Mandal Partha Roy Dipak Mandal Shuvranshu Kumar Rout
Organization:
Deep Foundations Institute
Pages:
8
File Size:
526 KB
Publication Date:
Sep 1, 2022

Abstract

Installation of a new scalping station with bunker, apron feeder, scalping screen, ramp -retaining wall and approach bridge was planned in an existing integrated complex of phosphate fertilizer at a remote place in West Africa. Rock phosphate ROM, transported from mines by a combination of 100 Ton and 150 Ton dumper, would be fed to a steel bunker having capacity of 180 m3. Different options were studied for retaining wall at the junction of ramp and approach bridge. Initially options with conventional RCC Retaining Wall, Gravity Retaining Wall with Precast Concrete Blocks and Reinforced Earth walls were studied. Option with Reinforced Earth was selected as this option was much more cost effective compared to other options. But real engineering challenges cropped up when competent execution contractors were not available nearby the site. To minimize the cost, an innovative option with Stepped Retaining wall was then studied. Geotechnical parameters of native soils, selected for the construction of the approach ramp were determined and it was found that with available poor geotechnical parameters of the native soils, design of stepped retaining wall would not be feasible with respect to available bearing capacity, subjected dead load, live load, operational load and earth pressure. A conscious effort was then made to make the design feasible by improving the geotechnical parameters of the retained earth of ramp near the retaining wall. In view of that, mix design with locally available materials like Silexite, Sand, Laterite, Gravel and Silt at different proportions was made and samples were tested in the laboratory to determine relevant geotechnical parameters. Based on the test results, a suitable mix was selected that had high shear strength, enhanced bearing capacity and improved coefficient of earth pressures. Design of stepped retaining wall was then made with the selected construction materials and construction completed. The plant was successfully commissioned in December. 2021.
Citation

APA: Biswajit Das Dr. Anup Kumar Mandal Partha Roy Dipak Mandal Shuvranshu Kumar Rout  (2022)  Design Of Cost-Effective Retaining Wall At The Junction Of Approach Bridge Over A Ramp

MLA: Biswajit Das Dr. Anup Kumar Mandal Partha Roy Dipak Mandal Shuvranshu Kumar Rout Design Of Cost-Effective Retaining Wall At The Junction Of Approach Bridge Over A Ramp. Deep Foundations Institute, 2022.

Export
Purchase this Article for $25.00

Create a Guest account to purchase this file
- or -
Log in to your existing Guest account