Design Development of the I-35 Capital Express Central Drainage Tunnels - NAT2024

- Organization:
- Society for Mining, Metallurgy & Exploration
- Pages:
- 11
- File Size:
- 806 KB
- Publication Date:
- Jun 23, 2024
Abstract
The I-35 Capital Expressway (CapEx) Central Drainage Tunnels will serve as a stormwater
collection system for the forthcoming I-35 Capital Express Central reconstruction project through downtown
Austin, Texas. The schematic level concept design included three tunnels, 10 to 14 ft ID, totaling 26,000 LF.
Constructability reviews during design development indicated issues with the concept design including
phasing of construction, conicts with future retaining walls, staging area concerns, and signicant mixed face
tunneling. The design was updated to mitigate these risks. The revised design includes two tunnels, both 22-ft
ID and totaling 33,000 LF, that will be mined almost entirely in rock.