Design, Construction, and Performance of the Temporary Earth Retention System at No. 9 Walton

- Organization:
- Deep Foundations Institute
- Pages:
- 10
- File Size:
- 653 KB
- Publication Date:
- Jan 1, 2017
Abstract
"No. 9 Walton is a new high-rise condominium building located in the Gold Coast area of Chicago. The adjacent building, Walton on the Park, featured 4 levels of below grade parking and utilized a secant pile wall with integral drilled shafts to support the exterior columns. The earth retention system (ERS) for No. 9 Walton also employed a secant pile wall in combination with drilled shafts. The excavation into the soft Chicago clays varied in depth from 9.75 m to 12.5 m (32 feet to 41 feet) below grade. The temporary excavation support used internal braces from the new secant piles to the existing foundation system of Walton on the Park to provide earth retention. Engineering teams for both projects worked together to design the bracing scheme and connections to ensure that the new excavation and internal bracing would not overstress any elements of the existing structure. Further complicating the project, immediately to the west of the project was a historic church founded on shallow spread footings which required underpinning to minimize movements.The project involved three different building owners, small values for acceptable wall movement, an extensive monitoring program and the challenges of merging two earth retention systems. The subsurface conditions at the site, the adjacent structures, the excavation, and the performance are described. A summary of the design methods and the expected movements of the ERS are discussed, and the performance monitoring system is described. Overall, the ERS performed better than expected with less than 1 inch of measured lateral wall movement during and after the excavation was completed. Measured performance of the ERS is compared to the predicted performance and to the performance requirements for the project.INTRODUCTIONNo. 9 Walton is a new high-rise condominium building in Chicago located in the Gold Coast. The building has 3 levels of below grade parking and 36 levels of living space above grade. Developers originally slated the project to be Phase 2 of the Walton on the Park development built in the mid 2000’s, using portions of the existing foundation system for development of the new structure. However, the housing market crash in 2007 prompted cancellation of Phase 2 of the Walton on the Park development. The property sat undeveloped until 2015 when design and construction for No. 9 Walton began under a new development and design team. The project team completed foundation excavation and below grade structures in 2016 with the first units of the building turned over to new homeowners in 2017.The structural design for No. 9 Walton consisted of reinforced concrete columns and slabs, supported laterally by a heavily reinforced concrete central core. Drilled shafts to rock supported the interior columns and core with the exterior columns and foundations integrally included in the earth retention system. The structure had a below-grade footprint of approximately 1,490 m2 (16,000 ft2). The general excavation extended 9.75 m to 12.5 m (32 feet to 41 feet) below street level with the deepest portions at the central building core mat foundation."
Citation
APA:
(2017) Design, Construction, and Performance of the Temporary Earth Retention System at No. 9 WaltonMLA: Design, Construction, and Performance of the Temporary Earth Retention System at No. 9 Walton. Deep Foundations Institute, 2017.