Design and Construction of the New VDOT Midtown Tunnel

- Organization:
- Deep Foundations Institute
- Pages:
- 4
- File Size:
- 15935 KB
- Publication Date:
- Jan 1, 2014
Abstract
"The Hampton Roads area encompassing the Norfolk, Virginia Beach and Newport News metropolitan region experiences some of the worst traffic congestion in Virginia. With continued growth of the ports and increasing demand, the Virginia Department of Transportation (VDOT) initiated the Downtown Tunnel/Midtown Tunnel/MLK Expressway Project, a complex undertaking critical to addressing the Hampton Roads area’s transportation needs. The project is a $2.1 billion Design/Build/Finance/Operate (DBFO) endeavor most notably involving the construction of a new two-lane vehicular tunnel utilizing the Immersed Tube Tunnel (ITT) method. The tunnel will pass under the Elizabeth River parallel to the existing Midtown Tunnel between Norfolk and Portsmouth, Va. It will be the largest design-build project constructed in the history of the Hampton Roads District.The New Midtown Tunnel will extend approximately 6,450 ft (1,966 m) along the north side of the existing tunnel where it ties into the existing Midtown Tunnel approaches in Norfolk and Portsmouth. It is being installed in a pre-excavated trench of which approximately 2,250 ft (686 m) required bracing on the Portsmouth side and approximately 1,000 ft (305 m) required bracing on the Norfolk side. The remaining 3,200 ft (975 m) of trench excavation was open cut dredging with laid back side slopes, optimized to reduce dredging, disposal and backfill quantities while also reducing the risk to the existing tunnel. The braced excavation portions of the tunnel alignment were divided into distinct segments which include: Portsmouth Approach Boat Section, Portsmouth Approach Cut-and-Cover Section, Portsmouth Dredge Section, Norfolk Dredge Section, Norfolk Approach Cut-and- Cover Section and the Norfolk Approach Boat Section. All “approach” excavations were performed in the dry and all “dredge” excavations were performed in the wet. Eleven ITT segments are being fabricated in the Sparrows Point Dry Dock facility in Baltimore, Md., and each 14,000 ton (12,700 tonne) segment is being towed approximately 220 mi (354 km) to the site. The ITT segments will extend under the Elizabeth River, with the deepest crossing 90 ft (27 m) at the Federal Navigation Channel. Once beyond the channel limits the ITT rises at an approximate 4.5% slope. Controlled screeding and element lowering operations will be performed primarily from floating barges."
Citation
APA:
(2014) Design and Construction of the New VDOT Midtown TunnelMLA: Design and Construction of the New VDOT Midtown Tunnel. Deep Foundations Institute, 2014.