Design and Construction of the NBAQ4 Project— First Urban EPB TBM Tunnel in Metro Manila - RETC2023

- Organization:
- Society for Mining, Metallurgy & Exploration
- Pages:
- 19
- File Size:
- 365 KB
- Publication Date:
- Jun 13, 2023
Abstract
The project involves the construction of a new aqueduct tunnel by an Earth Pressure
Balance TBM tunnel for the Novaliches-Balara Aqueduct No 4 (NBAQ4) project in
Metro Manila. It comprises a 7.3 km long and 3.1 m internal diameter tunnel that can
deliver up to 1,000 MLD of raw water and the tunnel passes under urban residential
and urban populated areas adjacent to and along Commonwealth Avenue. A new
reservoir intake structure was constructed in the La Mesa reservoir by a cofferdam
and the TBM breakthrough connected the reservoir to the outlet surge shaft structure
and the downstream pipe network system connecting to the Balara Water Treatment
Plant. The TBM incorporated a double articulated head configuration to allow tight
80 m radius curves to navigate some of the difficult alignment considerations. The
alignment passed very close to some existing foundations for MRT7 and needed to
clear several tight curves to remain within government land ownership. The project
excavated through the local Guadalupe weak rock formations and there was minimal
ground movements observed as a result of the work.