Construction Dewatering Challenges in Urban Environments

Deep Foundations Institute
Rafael A. Rivera
Organization:
Deep Foundations Institute
Pages:
4
File Size:
4861 KB
Publication Date:
Jan 1, 2017

Abstract

"Since the dawn of construction, there has been a need for excavations, which sometimes need to occur below the groundwater table. Excavations in themselves are difficult enough, with the myriad of requirements, such as engineered support of excavations, considerations for stability and numerous other concerns. Excavations executed in rural landscapes can be accomplished easily without significant consideration to accessibility, adjacent properties or structures, and construction limits and deformations. However, all of these factors can have an impact on excavation considerations in an urban landscape. When digging below the groundwater table, these conditions, along with concerns associated with groundwater drawdown requirements, discharge limitations, groundwater contamination, property limits, adjacent buildings and subsidence concerns, can lead an experienced dewatering contractor to consider diverse installation methodology and equipment to allow construction to occur below the groundwater table.534 W. 29th St. New York, N.Y.There are many things that must be considered when constructing a new high-rise building within a small property footprint measuring 25 ft (7.6 m) wide by 80 ft (24.4 m) in length. When you take into account that the foundation needs to go several feet below the groundwater table and that there are two existing multistory buildings with shallower foundations on either side of the proposed structure, this task now becomes much more difficult. Consideration of geology, groundwater levels, depths of excavation and shoring for the excavation becomes critical to the success of the project. On a regular basis, dewatering contractors confront similar situations in congested cities where available real estate is limited.To minimize the negative impacts of construction dewatering, it is important to mitigate the potential effects of construction dewatering to the surrounding buildings, sidewalks, underground structures, tunnels, subways and other existing infrastructure. Such an instance occurred at the project located at 534 W. 29 St. in New York City. On this particular project, the required drawdown was greater than the typical 15 ft (4.6 m) of suction lift, so a vacuumed can pump system was utilized. The tubing was connected to a vacuumed perimeter dewatering well-point system, which is a predrainage system that is installed prior to the start of excavation for the underpinning of the adjacent structures and for the overall foundation. Each well-point, which was composed of a PVC pipe that was 1.5 in (38 mm) in diameter by 25 ft (7.6 m) long, was drilled to a depth of about 23 ft (7 m) using a hollow stem auger and was installed around the perimeter at a centerto- center spacing of about 7.67 ft (2.3 m). In lieu of a traditional perimeter collection header, and to allow for greater flexibility for the contractor, the well-points were interconnected to a modified vacuum can pump system utilizing ¾ in (19 mm) drop tubes that were “spaghetti” around the perimeter."
Citation

APA: Rafael A. Rivera  (2017)  Construction Dewatering Challenges in Urban Environments

MLA: Rafael A. Rivera Construction Dewatering Challenges in Urban Environments. Deep Foundations Institute, 2017.

Export
Purchase this Article for $25.00

Create a Guest account to purchase this file
- or -
Log in to your existing Guest account