Case Study: Feather River West Levee Program Cutoff Walls

Deep Foundations Institute
Jared P. Williams Kyle R. Lackner
Organization:
Deep Foundations Institute
Pages:
12
File Size:
730 KB
Publication Date:
Jan 1, 2016

Abstract

"The Sutter Butte Flood Control Agency initiated the Feather River West Levee (FRWL) Program in 2010 to bring 35 miles of levee along the Feather River into compliance with applicable Federal and State standards for levees protecting urban areas. A combination of soil-bentonite cutoff walls, soil-cement-bentonite cutoff walls, and seepage berms will reduce flood risk by correcting under and through seepage deficiencies and remove more than 34,000 properties from the FEMA Special Flood Hazard Areas. The FRWL program includes a combined total of 7,744,803 square feet (SF) of cutoff wall planned to be constructed between 2013 and 2015. Cutoff wall construction methods to meet the design depths included conventional excavation to a depth of 85 feet and deep soil mixing for depths up to 120 feet. A key component of the FRWL program was the development of site specific mix designs using the design boring logs to evaluate the expected backfill gradation and permeability results. Issues that required a partnership between Contractors, Owner and Engineers included substantial Archaeological and Cultural Resource delays, significant depth changes due to a change in competent key, right of way acquisitions for abutting land, and the magnitude of the project in a resource limited industry.IntroductionThe Feather River watershed basin is located 50 miles north of Sacramento, CA and incorporates the agriculture producing communities of Yuba City, Live Oak, Gridley and Biggs. These communities are protected from flooding by levees that contain under-seepage and through-seepage deficiencies and were the cause of major failures in 1955, 1986 and 1997. The Feather River West Levee (FRWL) program was initiated by the Sutter Butte Flood Control Agency (SBFCA) in 2010. The long term objective of SBFCA is to correct the levee deficiencies and provide 200 year flood protection to more than 34,000 at risk properties located within the FEMA Special Flood Hazard Areas.Although FRWL contained a variety of construction components such as earthwork and pipe replacement, the slurry cutoff wall is the primary construction element for addressing under and through seepage deficiencies. From 2013 to 2015 approximately 6,649,210 SF of cutoff wall were installed using conventional excavation and deep soil mixing (DSM) techniques leaving 1,095,593 SF to be completed in 2016. The work was designed, solicited and constructed under two separate contracts, titled Project Area C and Project Area B&D. A summary of the contracts and cutoff wall quantities is presented in Table 1."
Citation

APA: Jared P. Williams Kyle R. Lackner  (2016)  Case Study: Feather River West Levee Program Cutoff Walls

MLA: Jared P. Williams Kyle R. Lackner Case Study: Feather River West Levee Program Cutoff Walls. Deep Foundations Institute, 2016.

Export
Purchase this Article for $25.00

Create a Guest account to purchase this file
- or -
Log in to your existing Guest account