Case History: Large Diameter Micropiles for the Highway 53 Relocation Project

- Organization:
- Deep Foundations Institute
- Pages:
- 10
- File Size:
- 3661 KB
- Publication Date:
- Jan 1, 2017
Abstract
"The Highway 53 relocation project in Virginia, Minnesota, involves construction of a very tall bridge across a currently inactive iron ore mine pit. The inactive pit is partially flooded and serves as the community’s drinking water source. The 1,132-ft long new bridge is a three-span, plate girder structure. Two intermediate, approximately 200-ft tall piers are located within the pit.The foundations for the two piers consist of groups of 30-in diameter piles which, despite the contradiction in terms, are essentially very large micropiles. Extremely challenging and highly variable subsurface conditions exist at the site, ranging from uncontrolled iron ore mine waste fill to some of the hardest rock on earth that can also be highly fractured and abrasive. Despite the conditions, large diameter (30-in) micropile foundations up to 175 ft deep were successfully installed using down-the-hole hammer methods and full-length permanent casing under an extremely aggressive construction schedule.Full-scale foundation load testing using the Statnamic rapid loading method was also conducted in support of the design and construction but under a separate pre-design phase contract. This paper describes the unique aspects of this foundation project, including design, construction, and load testing of the large micropiles.INTRODUCTION AND BACKGROUNDIn 1960, a segment of Trunk Highway 53 (TH-53) in Virginia, Minnesota, was built on land owned by iron ore mining interests. As part of the roadway easement agreement, Minnesota Department of Transportation (MnDOT) was to be given notice three years prior to termination of the easement. In 2010, MnDOT received notice that the mining interests wished to access the ore. Through negotiations in 2010, MnDOT and the mining interests agreed to a 2017 date for abandoning the existing section of roadway. During this period, MnDOT needed to procure project funding, satisfy environmental permitting requirements, and acquire new right-of-way to permanently reroute TH-53 and keep it open to traffic. This was no easy task due to the existing mine pits surrounding the area.The E-2 alignment option shown in Fig. 1 was ultimately selected for the rerouted highway in 2014. The new highway segment includes a three-span bridge across the currently inactive Rouchleau Mine Pit. The inactive pit is partially flooded and serves as Virginia’s drinking water source. The 1,132- ft long new bridge is a three-span, plate girder bridge. Two intermediate approximately 200-ft tall piers are located within the pit. Fig. 2 is a conceptual rendering of the bridge."
Citation
APA:
(2017) Case History: Large Diameter Micropiles for the Highway 53 Relocation ProjectMLA: Case History: Large Diameter Micropiles for the Highway 53 Relocation Project. Deep Foundations Institute, 2017.