Building the East-West Cross Drift Tunnel at Yucca Mountain

- Organization:
- Society for Mining, Metallurgy & Exploration
- Pages:
- 8
- File Size:
- 8164 KB
- Publication Date:
- Jan 1, 2000
Abstract
In April 1997, Kiewit/Parsons Brinckerhoff (K/PB) completed the 7,600-m (25,000-ft) primary access tunnel for the Yucca Mountain, NV proposed high-level nuclear waste site. K/PB then began boring an exploratory east-west cross drift tunnel at the site. The 2,681-m (8,796-linear ft)East-West Cross Drift Tunnel was excavated through volcanic tuffs having zones of incompetent rock using a rebuilt Robbins 5-m (16.4-ft)hard-rock tunnel boring machine(TBM) with a special arrangement of supporting equipment. This portion of the Yucca Mountain project was completed in eight months.