Bluestone Dam Safety Assurance Program: An OPA Runner Up

Deep Foundations Institute
Jeff Hopple
Organization:
Deep Foundations Institute
Pages:
4
File Size:
6434 KB
Publication Date:
Jan 1, 2014

Abstract

"Bluestone Dam in Hinton, W.Va., along the New River, is owned and operated by the U.S. Army Corps of Engineers (USACE). Completed in 1949, the dam is 165 ft (50 m) tall, 2,048 ft (624 m) wide, and encompasses a water shed that is 4,600 sq mi (11,914 sq km). The Bluestone Dam Safety Assurance (DSA) Program began in 2001, and is a multiple-phase construction project to upgrade the capacity and stability of the structure to meet the probable maximum flood event. Installing 216 high capacity rock anchors was a major feature of the work.The USACE selected Brayman Construction Corporation to perform Phase 2B of the construction modifications to the Bluestone Dam. Brayman was responsible for installing the high capacity rock anchors, which range in size from 3 to 61 strands and have a design load up to 2,145 kips (9,541 kN). Drill holes range in size from 6.5 to 15 in (16.5 to 38 cm), and required full length corrosion protection. Of the 216 anchors, 57 were installed on top of the dam to resist overturning and the remaining 159 were installed on the face of the dam at a 45-degree angle to resist sliding.To gain access to the face of the dam anchor locations, the project required dirt benches, excavations with temporary shoring, and steel platforms. To access anchors on the east and west abutment faces, the team excavated over 10,000 cu yds (7,645 cu m) of material. Support of these excavations included the design and installation of three soil nail walls with over 145 nails and 3,500 sq ft (325 sq m) of shotcrete. The project also called for a 780 ft (237 m) long steel platform to gain access to the spillway anchors. The Stratus Group designed the platform to support two 85 ton (80 tonne) crawler cranes and as many as five drill rigs that were the equivalent to a design load of 3.5 ton per sq ft (335 kN per sq m). Once the final platform design was approved, fabrication of roughly 3 million lbs (1,360 tonnes) of structural steel began. Brayman’s in-house fabrication shop, in conjunction with Dura-Bond Industries and Advantage Steel, collaborated to fabricate and install the platform in less than five months. Flexibility in the platform design allowed for sections of the platform to be lowered as much as 16 ft (4.9 m) to provide access to anchors at lower elevations along the spillway face. In addition to the main spillway platform, Stratus Group, Brayman, Dura-Bond and Advantage designed, fabricated and installed six other unique platforms to facilitate anchor construction on various areas of the dam."
Citation

APA: Jeff Hopple  (2014)  Bluestone Dam Safety Assurance Program: An OPA Runner Up

MLA: Jeff Hopple Bluestone Dam Safety Assurance Program: An OPA Runner Up. Deep Foundations Institute, 2014.

Export
Purchase this Article for $25.00

Create a Guest account to purchase this file
- or -
Log in to your existing Guest account