Blasting the Fulton Bottom River Crossing

- Organization:
- International Society of Explosives Engineers
- Pages:
- 5
- File Size:
- 111 KB
- Publication Date:
- Jan 1, 1979
Abstract
The City of Richmond, in an effort to improve sewage treatment facilities, designed an invert syphon to cross the James River at Fulton Bottom. The design criteria called for installation of two 36-inch pipe' lines at an elevation of -35 with the mean water level being at elevation 00. This paper discusses the actual method of construction used to blast the river bottom. Choice of excavation equipment, nature of the river, as well as the geological structure, were taken into consideration.
Citation
APA:
(1979) Blasting the Fulton Bottom River CrossingMLA: Blasting the Fulton Bottom River Crossing. International Society of Explosives Engineers, 1979.