Bertha Rescue Shaft – SR99 Tunnel

Deep Foundations Institute
Richard Hanke Lance Rasband
Organization:
Deep Foundations Institute
Pages:
4
File Size:
8554 KB
Publication Date:
Jan 1, 2015

Abstract

"Seattle Tunnel Partners (STP) started mining on Seattle’s SR99 tunnel on July 30, 2013, working slowly through a 15 ft (4.6 m) thick fiber-reinforced concrete headwall. Once through the headwall, the machine would move through roughly 400 lineal ft (122 m) of jet grout-improved soil at a rate slightly over 6 ft (1.8 m) per day. It was anticipated that once through the improved area, Bertha—the world’s largest tunnel boring machine—would move at a rate of 35 ft (10.7 m) per day. By the end of October 2013, Bertha had mined roughly 430 ft (131 m), averaging 4.73 ft (1.4 m) per day, and had begun mining within native soils. By the start of December 2013, tunneling reached the 800 ft (244 m) mark and Bertha averaged 12 ft (3.7 m) per day, achieving as much as 42 ft (12.8 m) of progress on some days. However, on December 6, 2013, Bertha began to stumble and all progress quickly came to a halt. Preliminary InvestigationInitial reports stated that an obstruction had stopped the machine in its tracks. Malcolm Drilling received an early morning call on Sunday, December 8, 2013, from STP to rapidly mobilize a Bauer BG-50 drill rig with crews to investigate what was hindering Bertha’s progress. Malcolm’s equipment and crews flew into action and were completely mobilized and operational by mid-week. The preliminary investigation involved installation of 10 deep dewatering wells to reduce the hydrostatic head within the ground around the machine and allow STP personnel to inspect the cutter head from within the shaft for presence of obstructions. By the close of December 2013, the wells were installed and the dewatering system was fully commissioned. STP crews were then able to inspect the cutter head and found small fragments of a steel pipe wrapped around the outside of the shield. The steel was apparently from an abandoned 10 in (0.25 m) diameter monitoring well casing previously installed by WSDOT (Washington State Department of Transportation) to monitor groundwater conditions for the design and planning of this very project. After the steel was cut out of the head and cleared from Bertha’s path, she attempted to move forward but was only able to manage a slow crawl"
Citation

APA: Richard Hanke Lance Rasband  (2015)  Bertha Rescue Shaft – SR99 Tunnel

MLA: Richard Hanke Lance Rasband Bertha Rescue Shaft – SR99 Tunnel. Deep Foundations Institute, 2015.

Export
Purchase this Article for $25.00

Create a Guest account to purchase this file
- or -
Log in to your existing Guest account