Bailey Mine Slurry Impoundment Longwall Subsidence Monitoring

- Organization:
- International Conference on Ground Control in Mining
- Pages:
- 12
- File Size:
- 3219 KB
- Publication Date:
- Jan 1, 1988
Abstract
Subsidence monitoring was conducted in proximity to the 1-A and 2-A longwall panels at Consol Pennsylvania Coal Co.'s (CPCC) Bailey Mine slurry impoundment. Monitoring fullfills federal Mine Safety and Health Administration (MSHA) mandated requirements. Construction of the monitoring network was completed between May and June, 1986. Monitoring was conducted before, during, and after mining of the panels between June, 1986 and February, 1987. The embankment was not deleteriously impacted by longwall mining.
Citation
APA:
(1988) Bailey Mine Slurry Impoundment Longwall Subsidence MonitoringMLA: Bailey Mine Slurry Impoundment Longwall Subsidence Monitoring. International Conference on Ground Control in Mining, 1988.