Backfill - Whatever it takes

- Organization:
- Society for Mining, Metallurgy & Exploration
- Pages:
- 3
- File Size:
- 199 KB
- Publication Date:
- Jan 1, 2002
Abstract
This paper provides an overview of Barrick Gold's Bullfrog underground mine backfill program. The Bullfrog underground mine was a gold mine that primarily used the underhand cut-and-fill mining method. The first portal was established June 18, 1991, and mining continued until Dec. 29, 1998. This paper begins with a discussion of the events that took place to reach about 1.8 kt/d (2,000 stpd) of backfill. It ends with a commentary of what was learned. The Bullfrog experience suggests that there are two essential factors to a successful backfill program: a well-graded aggregate supply and proper placing procedures.
Citation
APA:
(2002) Backfill - Whatever it takesMLA: Backfill - Whatever it takes. Society for Mining, Metallurgy & Exploration, 2002.