Assessment of Progressive Failure of an Expanded Concrete Segmentally Lined Tube Tunnel

- Organization:
- Society for Mining, Metallurgy & Exploration
- Pages:
- 11
- File Size:
- 1033 KB
- Publication Date:
- Jan 1, 2016
Abstract
"A section of a London Underground expanded segmental lined tunnel constructed in the 1970’s progressively deteriorated after 2001, with extensive radial joint spalling and mid-segment cracking. As part of the PPP contract Tube Lines Ltd and their partners carried out various analyses of the tunnel, including analysis of laser scans of the tunnel, geotechnical testing through the tunnel walls, geotechnical desk studies, real-time monitoring and even full-scale segment testing. This paper discusses the behaviour of the tunnel lining in this setting, the causes of failure and the lessons that can be learnt from this rare example of a tunnel which was progressively failing in service. It is finally noted that a replacement tunnel lining was installed during night-time possessions and completed in 2015. INTRODUCTION In 2003, Tube Lines Ltd. was established under a Public-Private Partnership (PPP) scheme to provide maintenance services and upgrade projects for London Underground (LU). The Deep Tube Tunnel Knowledge and Inspection Programme comprised the assessment of all tunnels, shafts and other underground structures. This included a number of lengths of tunnel constructed using segmental concrete linings. First used by LU in the 1960s, the savings both in cost and speed of construction led to concrete linings replacing cast iron for new tunnel construction in all but a few cases. During the initial scoping phase of this programme, inspections identified potential issues with the expanded concrete segmental linings on the Jubilee line. The inspections found a number of segments with surface spalling (Figure 1a), which did not appear on the post-construction defect records. These were generally relatively shallow, up to 40mm deep, spread over a wide area of segment. These were different to spalls caused by handling damage, which are typically localised at segment corners. Subsequent inspections over the following years identified an increasing number of segments with these types of spalls as well as an increased incidence of longitudinal mid-segment cracking (Figure 1b). The increasing occurrence of these defects was hypothesised to be caused by tensile stresses developing in the vicinity of the joint."
Citation
APA:
(2016) Assessment of Progressive Failure of an Expanded Concrete Segmentally Lined Tube TunnelMLA: Assessment of Progressive Failure of an Expanded Concrete Segmentally Lined Tube Tunnel. Society for Mining, Metallurgy & Exploration, 2016.