Application of Mining Width‑Constrained Open Pit Mine Production Scheduling Problem to the Medium‑Term Planning of Radomiro Tomic Mine: A Case Study - Mining, Metallurgy & Exploration (2024)
- Organization:
- Society for Mining, Metallurgy & Exploration
- Pages:
- 13
- File Size:
- 1835 KB
- Publication Date:
- Mar 28, 2024
Abstract
This article presents a novel approach to address the mining width-constrained open pit mine production scheduling problem
in the context of medium-term planning. A mathematical formulation is proposed to incorporate mining width constraints
into the production scheduling process, aiming to maximize the NPV of the schedule while ensuring enough room for the
operation of mining equipment. To tackle the computational challenges posed by large-scale instances of the problem, we
propose a method based on variable fixing and horizontal precedence generation. In this study, we apply the developed model
to real-world scenarios from Radomiro Tomic short-term mine planning problems such as optimizing the timing of major
truck maintenance and the impact of external factors, like the delay in the production of the Chuquicamata underground
project. Remarkable improvements are observed with the mining width-constrained model. Specifically, the mining width
satisfiability is enhanced from 2 to 60% compared to the traditional open pit mine production scheduling model, underscoring
the significance of incorporating these constraints. The proposed method showed good results reaching optimality gaps
within 5%.
Citation
APA: (2024) Application of Mining Width‑Constrained Open Pit Mine Production Scheduling Problem to the Medium‑Term Planning of Radomiro Tomic Mine: A Case Study - Mining, Metallurgy & Exploration (2024)
MLA: Application of Mining Width‑Constrained Open Pit Mine Production Scheduling Problem to the Medium‑Term Planning of Radomiro Tomic Mine: A Case Study - Mining, Metallurgy & Exploration (2024). Society for Mining, Metallurgy & Exploration, 2024.