Analysis and Performance of Sheet Pile Cofferdam under Demolition Blast Loads

- Organization:
- Deep Foundations Institute
- Pages:
- 8
- File Size:
- 3940 KB
- Publication Date:
- Jan 1, 2017
Abstract
"This paper will discuss the design analysis of sheet pile cofferdams for static and dynamic blast loads. Following construction of the new Willis Avenue Bridge across the East River between Brooklyn and Manhattan, in-river piers No. 9 and No. 10 from the former bridge were demolished, partially by explosive charges. The blast at Pier 10 was conducted first and though the demolition charge was relatively small, it gave confidence that the sheeting could be designed to resist the blast load. This paper primarily summarizes our analysis and performance of a sheet pile cofferdam at Pier 9 used to withstand the larger blast loads, contain the blast debris, and allow excavation of the pier below the existing river bed mudline. The program NLFlex was used to predict stresses and deformations of the cofferdams under dynamic blast loads, using simplified equations to estimate the underwater blast pressures. Specifically, the analysis focused on the stresses in the struts, waler beam, sheet pile interlocks and connection of the sheeting to the waler beam. Design included allowing plastic deformations and limited rupture of the sheet pile interlocks under the blast loading. Comparisons are made between stresses assessed by the dynamic finite element modeling and empirical relationships used within the industry. The performance of the system after the actual blast is discussed as well as details of the performance of welded vs. bolted connections within the system. IntroductionThe Willis Avenue Bridge is one of the major access ways from the Bronx into Manhattan. The location is shown on Figure 1. The original bridge constructed in 1901 was a swing bridge over the East River. The bridge was in disrepair and outdated with regards to its ability to handle the flow of traffic resulting in numerousaccidents.In 2007, Kiewit Constructors Inc./Weeks Marine, Inc., A Joint Venture was selected to construct a replacement bridge. The $612 million project included construction of a new bridge just to the south of the original bridge. The most notable aspect of the construction was floating and lifting the new 350 ft. long swing span in place as a single piece. However, another significant challenge was using blasting to demolish two of the abandoned piers which were within the East River. The blast would be near existing structures in both Manhattan and Brooklyn and would be within 30 ft. of the new bridge."
Citation
APA:
(2017) Analysis and Performance of Sheet Pile Cofferdam under Demolition Blast LoadsMLA: Analysis and Performance of Sheet Pile Cofferdam under Demolition Blast Loads . Deep Foundations Institute, 2017.