A Follow-Up Report on Longwall Coal Mining at Durban Navigation Collieries (Pty.) Limited

- Organization:
- The Southern African Institute of Mining and Metallurgy
- Pages:
- 11
- File Size:
- 1633 KB
- Publication Date:
Abstract
INTRODUCTION To prepare the reader adequately, reference should be made to the paper 'The Pioneering of Fully Mechanized Longwall Coal Mining in South Africa' by R. T. Naude and M. J. Deats, published in the February, 1967, edition of the Journal. At the time mechanized longwalling had been proved operationally feasible with encouraging results since its inception in South Africa in mid 1965. Subsequently, further top seam panels were successfully extracted with improved productivity and with some modification to equipment. In 1968, after an overseas visit by mine officials, equipment specific to suit local conditions was acquired and lower seam trials commenced. Despite initial obstacles and difficulties the first panel was successfully mined. Modification and improvements to equipment and techniques resulted in the second lower seam panel being extracted economically during 1969-1970 and with productivity exceeding even that of top seam faces. During extraction of the second lower seam panel, gradual and complete surface subsidence occurred over the panel without affecting face operations. Rock mechanics investigations had originally indicated some uncertainty regarding adverse dolerite sill behaviour which could have caused longwall mining to be hazardous. All such doubts have now been removed. RESUMÉ AS AT FEBRUARY, 1967 Mechanized longwalling was introduced in 1965 on an experimental basis in an effort to improve productivity in the newer area of the mine and to increase the quality of the comparatively dirty run of mine feed to the washing plant. In addition advantages could be predicted in the long term by better utilizing reserves of straight coking coal and increasing the life of the mine. The top seam unit was obtained on a rental basis and by the beginning of 1967, two panels, the first having a face length of 215 m, a panel length of 345 m, seam section of 1 219 mm, and the second the same face length, a panel length of 453 m and a seam section of 1 067 mm had been successfully longwalled. At this stage a best month of 24 602 metric tons with an average of 17 364 metric tons per full working month could be reported. Results were sufficiently encouraging for the company to exercise its right to acquire the equipment as its own asset and from 1967 onward, the unit has operated on this basis. From the point of view of rock mechanics, the dolerite sill over the first two panels was known to have 'bridged', only the material below the base of the sill having truly 'goafed'. No adverse pressure effects had significantly affected face operations except for two 'bumps' towards the end of operations in each panel. Gate road maintenance presented no problem. The strong inflows of water experienced on the first face were now known to be associated with an isolated water bearing fault plane and were not experienced on the second face. TOP SEAM EXPERIENCE - MAY, 1966, TO DATE Panel 2 (February, 1966, to November, 1966) The operations in panel 2 (see Fig. 1 for location of panels) continued uneventfully until the final month in this panel. At this stage, the chocks behaved most inconsistently often lowering under the weight of the canopies alone. Roof trouble became so severe that the unit was unable to produce adequately and blasting of chocks became a daily occurrence. Finally 24 m short of the planned limit it was decided that a complete overhaul was the only solution and the extraction operations commenced. At this time, the only fatal accident associated with longwalling occurred when a Non-White inadvertently fell into the panzer conveyor transfer point at the main gate. Some gate road difficulties in this panel were overcome by bolting tapes to the roof as decking and allowing them to pass over the gate chocks and collapse into the goaf. Two cribbed roof falls were also negotiated by the gate chocks at the face ends without undue difficulties. It was decided in the light of maintenance problems encountered on this face that the best solution would be to appoint a foreman solely in charge of face maintenance crews. This step has to a large extent contributed to success achieved subsequently. Panel 2-face length 213 m panel length 456 m cutting height 1 092 mm average monthly output 16 443 t best month 19 130 t Panel 3 (December, 1966, to June, 1967) By the end of 1966 results were sufficiently encouraging for the company to exercise its right to acquire the equipment. This was negotiated and the unit has operated as such to the present date. Prior to installation in panel 3, all face equipment was thoroughly overhauled underground and the chocks boost-tested to yield-load. The costs of overhauling, including almost complete hose replacement, were much higher than anticipated. Advice had been received that complete hose replacement was common practice after +/- 18 months' operation. Shortly after commencement of operations in panel 3 the chocks again failed as they had towards the end of panel 2. At this stage, the suppliers advised that the valve gear should have been repaired during the overhaul as the needle and seat seals could no longer be relied upon. This operation was impossible to carry out on the face and would have been e1ttremely time consuming. Fortunately a new type of valve gear was then available from the suppliers, termed the capsule-type valve, and a complete change over could be made on the face. The encapsulated valve has a delrin pad sealing over a raised
Citation
APA:
A Follow-Up Report on Longwall Coal Mining at Durban Navigation Collieries (Pty.) LimitedMLA: A Follow-Up Report on Longwall Coal Mining at Durban Navigation Collieries (Pty.) Limited. The Southern African Institute of Mining and Metallurgy,