A Case Study Of The Strathcona Sound Project (A Non Recourse Project Financing)

- Organization:
- The American Institute of Mining, Metallurgical, and Petroleum Engineers
- Pages:
- 12
- File Size:
- 381 KB
- Publication Date:
- Jan 1, 1985
Abstract
INTRODUCTION The small mining company faces the dilemma of how to finance the development of its properties. Many of these small companies don't have the financial resources to pay for development costs from their own funds and frequently they do not even have the financial strength to permit them to borrow the money needed for development. A project financing can sometimes be arranged in such a way as to solve this dilemma. A typical project financing will not provide the answer to the "little guy's" problem because most project financings require that the sponsors of the project provide completion undertakings and sometimes other undertakings. These undertakings are often a prerequisite to obtaining financing, and if the sponsor is not financially strong enough to provide the comfort that the lenders require, then the sponsor will have difficulty obtaining financing no matter what undertakings are offered. However, with a little imagination and the right set of circumstances, a project financing can sometimes provide the solution to the small mining company's problem. The Strathcona Sound Project is unusually suited as a case study because the sponsor, Mineral Resources International Limited,(MRI) was able to arrange a project financing for the development of the project even though the lenders probably would not have been willing to loan a similar amount of money direct to MRI based on the full faith and credit of MRI's balance sheet. The way that MRI was able to arrange this financing makes for an interesting story. THE CASE In early 1974, MRI owned 100% of a small to medium sized zinc - lead - silver massive sulfide deposit (Property) located 475 miles north of the Arctic Circle less than two miles from deep water on Strathcona Sound which is a shipping zone in the Canadian Arctic. The Property was situated at a desolate location except for an Eskimo settlement (Arctic Bay) which was about 20 miles west of the Property. In other words, the project required that complete infrastructure would need to be installed in this far northern location. Independent reserve and feasibility studies (Study) had been completed on the Property which confirmed a total of 6,825,000 tons of reserves classified and summarized as shown below on Table I: [ ] These reserves were based on 229 diamond drill holes totalling 58,909 feet and were established on a cut-off grade of 7% zinc and a minimum mining height of seven feet. The overall mining recovery rate was estimated at not less than 85% and not more than 90%. The feasibility study indicated that it would cost an estimated $45,044,000 to develop an underground mine, a concentrator, a town-site, a power plant, storage facility, loading dock, a tailings disposal area and an airstrip on the Property with an annual capacity of 525,000 tons of ore per year. The construction period was expected to take two years and projected capital costs were broken down as set forth below on Table II:
Citation
APA:
(1985) A Case Study Of The Strathcona Sound Project (A Non Recourse Project Financing)MLA: A Case Study Of The Strathcona Sound Project (A Non Recourse Project Financing). The American Institute of Mining, Metallurgical, and Petroleum Engineers, 1985.