A Case Study, Design Change from Spread Footing to Drilled Shafts

Deep Foundations Institute
Mohammad Ayub Iqbal Drew M. Kurtz Sara F. Frailey Jeff L. Rai
Organization:
Deep Foundations Institute
Pages:
8
File Size:
2699 KB
Publication Date:
Jan 1, 2016

Abstract

"This paper presents the foundation changes made for a five-span bridge over the Lehigh River constructed as a design-build project. During excavation within the cofferdam at Pier 2 for the construction of a spread footing to bear on rock, it proved extremely difficult to control the water entering the excavation as the sheet pile tips were variable due to the bedrock pinnacles and a weathered rock zone above the top of rock allowing water to pass below the sheeting. Water also entered from the bottom of the excavation, possibly due to the presence of solution openings within the dolomite bedrock. After repeated failures to achieve subgrade elevation and maintain a dry excavation, a design change to drilled shafts was made. Additional borings were performed for each of the shaft locations to explore the area underlain by karstic dolomite rock. A seal consisting of tremie concrete with adequate weight was placed to counter the differential head of water and the three drilled shafts (with minimum 25 feet [7.62 meter] rock sockets) were installed. A detailed construction sequence was followed and advanced quality control testing was performed. The construction of Pier 2 was completed successfully.1. INTRODUCTIONThis paper presents the description of the design change made from spread footing to drilled shafts as a result of site conditions encountered during the excavation for the spread footing for a bridge pier in the Lehigh River in Allentown, Pennsylvania. The bridge is located in an area underlain with dolomite rock, presenting karstic conditions including irregular top of rock and solution openings that provided high hydraulic conductivity below the top of rock. Also, the presence of a zone of weathered rock and pinnacle rock prevented the advancement of sheet piles when constructing the cofferdam. Thus, the difficulties of advancing the excavation to the desired spread footing level resulted in the design change to drilled shafts during construction. Since the project was Design-Build, the design could be changed by a collaborative process through the efforts of the Contractor, its geotechnical and structural engineers, and the State's (owner's) geotechnical and structural engineers and construction management staff."
Citation

APA: Mohammad Ayub Iqbal Drew M. Kurtz Sara F. Frailey Jeff L. Rai  (2016)  A Case Study, Design Change from Spread Footing to Drilled Shafts

MLA: Mohammad Ayub Iqbal Drew M. Kurtz Sara F. Frailey Jeff L. Rai A Case Study, Design Change from Spread Footing to Drilled Shafts. Deep Foundations Institute, 2016.

Export
Purchase this Article for $25.00

Create a Guest account to purchase this file
- or -
Log in to your existing Guest account