70-Foot-Deep Sheet Pile Cofferdams Driven by the Press-In Piling Method

- Organization:
- Society for Mining, Metallurgy & Exploration
- Pages:
- 7
- File Size:
- 1015 KB
- Publication Date:
- Jan 1, 2016
Abstract
"70-foot deep rectangular-shaped bulkheads were built with sheet piles as launching and receiving shafts for a pipe jacking operation for new underground waterlines in a densely populated section of Los Angeles, California. The Press-in Piling Method was specified to drive 95-foot long sheets (a record for the method) to form the bulkheads for the Los Angeles Department of Water and Power’s LA-29 (DWP) Connection Modification and Pipe Jacking. The piling was chosen because of its very low noise and practically vibration-free nature since the site is surrounded by houses, an apartment complex, and existing water lines. The out front areas of the bulkheads were grouted to let the TBM go through without major ground water leaks. Hydrophilic foam grout was also injected in addition to welding steel scab plates on the inside to seal them to achieve sufficient watertightness behind a few split interlocks. BACKGROUND This project was located in the Crescent Heights area of Los Angeles which is a few miles south of Beverly Hills. The project represents the completion of the last phase of the Stone Hollywood Trunk Line. This was an 8-mile long water trunk line that averaged 60 inches in diameter and was built to improve the reliability of the DWP’s major water system. This section of the project involved driving 2 deep shafts to allow for the installation of a 350-foot-long 72-inch steel casing using microtunneling construction. See Figure 1 for the shaft locations and the tunnel alignment. The challenge for the project was that this water line would have to pass beneath the Hollyhills buried box drain (15 feet high by 20 feet wide). Further complicating the construction was the soils beneath the drain. The DWP chose to drive the tunnel at a depth of approximately 65 feet to ensure that the ground conditions were uniform and suitable for the microtunneling equipment. There were two previous attempts to construct this work which failed because of poor ground conditions and very high water levels. This third attempt was critical because the DWP could not afford to have another failure due to the fallout with the residents being impacted by the project."
Citation
APA:
(2016) 70-Foot-Deep Sheet Pile Cofferdams Driven by the Press-In Piling MethodMLA: 70-Foot-Deep Sheet Pile Cofferdams Driven by the Press-In Piling Method. Society for Mining, Metallurgy & Exploration, 2016.